(a) Application. An Application for a Surface-Mounted Facility Site Permit shall contain such information as the Department shall determine is necessary by order or regulation.
(b) Time for Application.
(1) If, pursuant to Section 2703(b), the Department did not require the Applicant to follow the Pre-Application Approval Process, an Application may be submitted immediately upon the Department's determination there is only one feasible location for the proposed Surface-Mounted Facility.
(2) If the Pre-Application Approval Process has been completed, an Application may be submitted to the Department as further described below:
(A) If a timely protest to a Notice of Intent was not submitted, immediately upon the expiration of the protest period.
(B) If a timely protest to a Notice of Intent was submitted, immediately upon receipt of the Director's decision issued after the hearing.
(c) Completion Notice.
(1) Upon receipt of an Application, the Department shall first determine whether the Application is complete. The Department will notify the Applicant within 3 days whether the Application is complete.
(2) An Application is not complete if the Applicant does not specify that the location for the proposed Surface-Mounted Facility has been approved by the Department, or that the Department has waived the required Pre-Application Approval Process pursuant to Section 2703(b), and that the Applicant will comply with all of the Conditions of approval imposed by any City department or in a Director's decision issued after a hearing.
(d) Reasons for Denial.
(1) If, pursuant to Section 2703(b), the Department waived the Pre-Application Approval Process for its proposed location for a Surface-Mounted Facility, the Department may deny an Application at the Applicant's selected location if the Applicant rejects any of the Conditions proposed by any City department that reviewed the Application.
(2) If a timely protest was not submitted, the Department may deny an Application at the location identified in the Notice of Intent if the Applicant rejects any of the Conditions proposed by any City department that reviewed the Application.
(3) If a timely protest was submitted, the Department shall deny an Application if the Director has not approved a location for the proposed Surface-Mounted Facility or if the Applicant rejects any of the Conditions set forth in the Director's decision.
(e) Approval of Location.
(1) If, pursuant to Section 2703(b), the Department waived the Pre-Application Approval Process for its proposed location for a Surface-Mounted Facility, the Department shall approve the location identified by the Applicant.
(2) If no protest was submitted, the Department shall evaluate the proposed Preferred Locations in the order ranked by the Applicant.
(3) If a protest was submitted, the Department shall approve the proposed location contained in the Director's decision.
(f) Final Determination. The Department shall finally approve or deny an Application at the Applicant's selected location within 2 days after the Department's determination that the Application is complete.