8.1.1   EXISTING DEFICIENCY IMPROVEMENTS
The previous chapter described deficiencies in the system based on existing conditions. Improvements that address those deficiencies are described in Table 8-1. Included in the table are project numbers from the 2016 Master Plan to allow for easy comparison between plans.
Table 8-1
Existing Deficiency Improvements
ID
Previous ID
Problem
Proposed Solution
ID
Previous ID
Problem
Proposed Solution
DP-1
D-11
Increase transmission capacity from pump station and complete pipeline in north side of 7800 South
Install 1,590 feet of 8-inch pipeline in 7800 South between 5360 West and 5100 West, 355 feet of 12-inch pipe between 5100 West and 5060 West, 1,175 feet of 16-inch pipe between 5060 West and 4880 West, and 480 feet of 12-inch pipe between 4880 West and 4800 West, and 70 feet of 16-inch pipe across 7800 South at 5060 West
DP-2
D-12
High water user does not have service redundancy
Install 1,530 feet of 10-inch pipe in the business access road beginning at about 4980 West Old Bingham Highway and from that point north to about 9295 South then west to Winter Berry Drive, then north in Winter Berry Drive to connect to the existing 12-inch pipeline in Wild Acres Drive.
DP-3
D-18
Zone 2a Transmission
Install 7,900 feet of 12-inch pipeline in 2700 West between 6600 South and 7800 South
DP-4
D-19
Low pressures in Zone 3
Pressure Zone 3 & 4 boundary relocation including the installation of 4,605 feet of 8-inch pipe beginning at 4900 West 9000 South and proceeding north to 8900 South 4910 West and in McGinnis Lane between 4910 West and New Bingham Highway.
DP-6
D-24
Separate Pressure Zones 3 and 4
Install 1,900 feet of 10-inch pipe in Swift Water Way between Grizzly Way and 7800 South
DP-7
D-27
The City prefers to have transmission pipelines on both sides of 5 lane roads
Install 7,900 feet 12-inch pipe in 7000 South between 2700 West and 1300 West
PZ-1
D-17
Low pressures in Zone 1
Pressure Zone 1 west of 2700 West should be segregated to form a new Zone 2a and 2b pressure zones. Service line PRVs need to be checked prior to change over as pressures will increase significantly.
PZ-2
D-20
Low pressures in Zone 5
Move phase 3 of the Maples at Jordan Hills Subdivision to Zone 6
PRV-1
D-22
New PRV needed in 9000 South
Install a new 12-inch PRV at about 6730 West 9000 South