The capacity analysis, described in Chapter 6, sets the foundation for the capital improvement program (CIP). The CIP focuses on alleviating the collection system capacity deficiencies. The intent of the CIP is to serve as a working document which the City can follow to update the capacity deficient sections of the collection system.
When fully implemented, the CIP illuminates hydraulic capacity deficiencies in the collection system to convey peak flows to the wastewater treatment plant (WWTP). This section provides a discussion of the sewer replacement criteria, modeling assumptions, cost criteria and the recommended improvements included in the CIP.