Skip to code content (skip section selection)
Compare to:
West Jordan Overview
West Jordan, UT Code of Ordinances
West Jordan General Plan
West Jordan Midvale 3 Stations Plan
West Jordan Parks and Recreation Master Plan
West Jordan Sanitary Sewer Master Plan
West Jordan Storm Drainage Master Plan
West Jordan Active Transportation Plan
West Jordan Transportation Master Plan
West Jordan Water Master Plan
IMPLEMENTATION PLAN
Based on the system improvements identified above, Table ES-12 lists improvement projects that are recommended within the next 10 years, the budget required to complete those projects, and the recommended timing of those projects. Figure ES-4 shows these projects compared to the recommended capital budget range. Costs shown in this figure include an assumed inflation rate of 3% per year.
Table ES-12
Implementation Plan Summary
ID
Project
Cost Estimate
Priority
Year
ID
Project
Cost Estimate
Priority
Year
Capital Projects - Pipelines
DP-1
Increase transmission capacity from pump station and complete pipeline in north side of 7800 South
$1,401,000
11
2030
DP-2
High water user does not have service redundancy
$553,000
10
2029
DP-3
Zone 2a Transmission
$3,004,000
8
2028
DP-4
Low pressures in Zone 3
$1,601,000
9
2029
DP-6
Separate Pressure Zones 3 and 4
$687,000
12
2030
DP-7
The City prefers to have transmission pipelines on both sides of 5 lane roads
$3,004,000
13
2030
TP-8
Source transmission is needed for Terminal Tank
$4,170,000
With S-3
2024
TP-9
Source transmission is needed for new Zone 5 North Tank
$1,098,000
With S-4
2027
TP-10
Outflow transmission is needed for new Zone 5 North Tank
$1,510,000
With S-4
2026
TP-11
Transmission is needed for new Zone 5 South Tank
$2,750,000
With S-3
2024
TP-12
Transmission is needed for new Zone 7 North Tank
$1,900,000
With S-6
10+
TP-13
Transmission is needed for new Zone 7 South Tank
$1,390,000
With S-7
10+
TP-14
Transmission is needed on north side of Maples area
$400,000
With S-4
2027
TP-15
Additional transmission capacity is needed
$2,510,000
With S-3
2024
TP-16
Additional transmission capacity is needed
$1,380,000
With S-4
2027
TP-17
Transmission is needed for new Zone 5 South BPS
$1,200,000
With S-3
2024
TP-18
Transmission is needed from the south end of Zone 5 to the north end.
$2,220,000
With Development
2025
FF-1
Insufficient fire flow at West Jordan Elementary School
$250,000
1
2022
FF-2
Inadequate fire flow to residential area
$480,000
2
2023
FF-3
Inadequate fire flow to residential area
$540,000
3
2025
FF-4
Inadequate fire flow to residential area
$150,000
4
2025
FF-5
Inadequate fire flow to residential area
$210,000
5
2025
FF-6
Inadequate fire flow to residential area
$660,000
6
2026
FF-7
Inadequate fire flow to residential area
$340,000
7
2026
PZ-1
Low pressures in Zone 1
$50,000
With P-3
2028
PZ-2
Low pressures in Zone 5
$10,000
14
2031
PRV-1
New PRV needed in 9000 South
$230,000
15
2031
PRV-2
Need PRV in Future 7000 South Transmission pipeline
$230,000
With S-4
2027
PRV-3
Need PRV in Future 7000 South Transmission pipeline
$230,000
16
2031
Sub-Total
$34,158,000
Capital Projects - Booster Pump Stations
PS-1
Zone 5 South Booster Station
$3,300,000
With S-4
2026
PS-2
Zone 5 North Booster Station
$3,300,000
With S-3
2024
PS-3
Zone 7 North Booster Station
$2,800,000
With S-6
2031
PS-4
Zone 7 South Booster Station
$2,800,000
With S-7
10+
PS-5
Additional Zone 2 Booster Pump
$150,000
1
2027
PS-6
Additional Zone 3 Booster Pump
$150,000
2
2028
PS-7
Additional Zone 4 Booster Pump
$150,000
3
2029
Sub-Total
$12,650,000
Capital Projects - Storage
S-1
Additional Storage Required in Zone 1
$10,400,000
1
2022
S-2
Additional Storage Required in Zone 3
$6,000,000
Complete
2021
S-3
Additional Storage Required in Zone 5
$13,800,000
3
2023
S-4
Additional Storage Required in Zone 5
$13,800,000
4
2026
S-5
Additional Storage Required in Zone 6
$10,400,000
2
2023
S-6
Additional Storage Required in Zone 7
$6,900,000
6
10+
S-7
Additional Storage Required in Zone 7
$6,900,000
7
10+
S-8
Additional Storage Required in Zone 4
$13,800,000
5
2028
Sub-Total
$82,000,000
Capital Projects - Wells
W-1
Equip Well 8
$1,500,000
1
2025
Sub-Total
$1,500,000
Rehab & Replacement
RR-1
Aging system components requires rehab & replacement (Annually)
$5,000,000
1
2022
Sub-Total
$50,000,000
TOTAL
$180,308,000
 
As can be seen in the figure, the recommended implementation plan tracks relatively closely to the identified sustainable range of system investment 3 . Thus, completing these projects following the schedule proposed in the implementation plan will accomplish the needed improvements identified in the master plan and also keep the City responsibly funding the system at the level necessary to provide quality ongoing service.
3 The one notable exception to this overall conclusion is in the first few years when significant expenditures associated with storage will require investment above and beyond recommended long-term funding levels. In this case, it is recommended that the City consider bonding for at least a portion of these costs to address cash flow needs and keep annual expenditures consistent with long-term funding recommendations.
Figure ES-4
10 Year Expenditures