(a) A person making an application for reclaimed water service shall submit the following information to the director for his or her approval, prior to construction or retrofit of an onsite facility that will use or receive reclaimed water:
(1) Design drawings and specifications which must be in compliance with the city’s policies and regulations;
(2) Drawings of the final installed onsite facility and the entire proposed use area;
(3) Proof that the user will be compliant with Chapter 12.5, Article 5, Division 3 Cross-Connection Control and has the required backflow prevention assembly on the reclaimed water service line; and
(4) Proof, as requested by the director, that the user has sufficient storage facilities for the reclaimed water and will be in compliance with Chapter 210.
(b) The director may issue written notice to the applicant to proceed with construction and/or retrofit upon satisfaction that the applicant meets or shall meet the minimum design and operation standards for reclaimed water service.
(c) After completion of the construction or retrofit of the onsite facilities for reclaimed water service, the applicant must make a written request for inspection by the city. The inspection shall include the cross-connection control and an operational test.
(d) The director shall grant the user approval of reclaimed water onsite facilities if:
(1) The director determines that the applicant meets the city’s minimum design and operation standards; and
(2) The system passes the inspection and the operational tests of the cross-connection control.
(Ord. 19543-02-2011, § 1, passed 2-8-2011)