(a) Application for a sidewalk repair or installation permit shall be made on forms furnished by the city.
(b) Applications may be made by mail or telephone. Such applicants must have a cash deposit with the city sufficient to cover fees, or include fees with the mailed application.
(Ord. No. 2657, § 1, 10-19-64)
The conditions set forth in section 25-20 may be required before issuance of a permit.
(Ord. No. 2657, § 1, 10-19-64)
(a) Permit fees for sidewalk installation, street excavations, improvements to unimproved portions of public right of way, curb cuts, driveway installations and repairs, are defined in the Planning and Permitting Fee Schedule, UDC Admin Manual, Sec. 4.
(b) A permit shall cover only contiguous construction and the work to be done as one (1) continuous operation. Such fees shall be tripled if work is commenced prior to obtaining permit. Payment of triple fees shall not waive other penalties.
(Ord. No. 2657, § 1, 10-19-75; Ord. No. 6967, § 1, 6-6-88; Ord. No. 7212, § 1, 6-12-89; Ord. No. 8727, § 1, 9-9-96; Ord. No. 12108, § 2, 6-18-24)
Applicants shall follow the standard provisions herein set forth for sidewalk construction:
(1) Minimum width: Four (4) feet.
(2) Beginning distance from property line: Two (2) feet.
(3) Grade: To follow a line sloping up and away from the top of the curb at a slope of one-fourth inch per foot.
(Ord. No. 2657, § 1, 10-19-64)
The city engineer may authorize variances from standard sidewalk provisions where no curb exists or when unusual topographical conditions, nature of existing construction, or similar factors would make adherence to standard provisions unreasonable.
(Ord. No. 2657, § 1, 10-19-64)
No sidewalk shall be installed unless a grade and line are established therefor. If no grades or lines are available, sidewalks may be installed, but they shall be removed, modified or replaced to conform to grades and lines when established by the city at the sole cost of the property owner abutting said sidewalk.
(Ord. No. 2657, § 1, 10-19-64)
All work shall be subject to inspection by the city, during construction and upon completion.
The street and sidewalk inspector shall be notified by the permittee after forms are set, and no concrete shall be poured or further construction started until approved by the inspector.
(Ord. No. 2657, § 1, 10-19-64)