Sec. 25-20. Conditions for obtaining permit.
Applicant for a permit and/or his agent and/or the contractor doing the work may be required, before the issuance of the permit, to:
   (1)   Furnish bond or insurance to hold the city harmless and/or fee of liability arising out of the work.
   (2)   Prove he is not delinquent in payments due the city on prior similar work.
   (3)   Prove he is competent and equipped to do the proposed work.
   (4)   Show he has proper licenses to do the work.
   (5)   Submit a plan of subject property and adjacent properties showing existing curb cuts, driveways and their sizes.
(Ord. No. 2657, § 1, 10-19-64)
Sec. 25-21. Permits required from other city departments or governmental agencies.
Permits are required for work done by city departments other than the public works department and by other governmental agencies. No permit fee shall be charged for such permits.
(Ord. No. 2657, § 1, 10-19-64)
Sec. 25-22. Conformance to rules and regulations.
All work shall conform to specifications and to the rules and regulations established by the director of public works and to instructions issued pursuant thereto by the street and sidewalk inspector.
(Ord. No. 2657, § 1, 10-19-64)
Sec. 25-23. Inspection of work.
   (a)   All work shall be subject to inspection by the city.
   (b)   The street and sidewalk inspector shall be notified by permittee before starting work, and before starting backfill, and upon completion of the work. The permittee shall not proceed with any further work in each instance until being authorized by the street and sidewalk inspector.
(Ord. No. 2657, § 1, 10-19-64)
Sec. 25-24. Barricades; notice.
   (a)   The applicant shall adequately barricade work in accordance with the latest edition of the "Manual on Uniform Traffic Control Devices," including additions by the city, and shall install sufficient warning lights and signs to protect the public. The applicant shall notify and obtain approval from the traffic engineer seventy-two (72) hours in advance, except in emergencies, before closing or barricading any street or public right-of-way, or portion thereof.
   (b)   Three (3) copies of the "Manual on Uniform Traffic Control Devices," including additions by the city, shall be filed in the office of the city clerk and are made public records and shall be available for public use and inspection during regular office hours.
(Ord. No. 2657, § 1, 10-19-64; Ord. No. 6148, § 5, 1-7-85; Ord. No. 10140, § 1, 4-12-05)
Sec. 25-25. Resurfacing.
   (a)   Unless otherwise stipulated in the permit, all pavement resurfacing after excavation shall be done by the city. The city shall make a charge for such work according to a schedule of costs established by the director of public works, copies of which schedule shall be kept on file with the city clerk, as revised from time to time.
   (b)   The applicant shall pay in advance the estimated change. Any difference shall be corrected after work is completed.
(Ord. No. 2657, § 1, 10-19-64)
Sec. 25-26. Permit expiration.
A permit shall expire for work not started within thirty (30) days or completed within sixty (60) days after issuance of a permit, and a new permit shall be required before beginning or completing the work.
(Ord. No. 2657, § 1, 10-19-64)
Sec. 25-27. Backfilling and filling.
Backfilling and filling material and the method of filling and backfilling shall meet city specifications. Excavated material not suitable for backfilling shall be removed from the site.
(Ord. No. 2657, § 1, 10-19-64)