§ 35-83 CRITERIA FOR PER ACRE CHARGE SEWER MAINS; DEVELOPER INITIATED PROJECT.
   (a)   A per acre charge may be collected for an approach sewer main of any length and size, constructed by a developer, provided the approach sewer main meets the following requirements:
      (1)   The proposed development to be served by the approach sewer main must be less than or equal to one-third of the calculated sewer basin area to be served by the approach sewer main; and
      (2)   The sewer basin area to be served by the approach sewer main shall be equal to or greater than 1,000 acres.
   (b)   It is the developer’s responsibility to provide all necessary information for a determination to be made if a per acre charge is appropriate for any given construction project.
(Ord. 15095, § 1, passed 5-14-2002; Ord. 21251-05-2014, § 2, passed 5-20-2014)