Where an industrial or commercial plant or premises discharges its effluent to a manhole used as a gauging and sampling point, and the effluent is of such a volume and duration that installation of hydraulic equipment cannot be made until the plant or premises ceases its operation by weekend closedown, the costs of making the installation, involving overtime pay, shall be at the expense of the owner of the plant or premises. If such owner elects to make the hydraulic installation with his or her personnel, the installation shall be set up in a manner approved by duly authorized employees of the village. If more than the standard five-day, 40-hour week is required for village personnel to properly gauge, sample and analyze the discharged effluent, the extra costs shall be at the expense of the owner of the property.
(`80 Code, § 1036.15) (Ord. 1584, passed 10-18-82; Ord. 2019, passed 12-20-93)