For pipe sizes greater than 4 inches (100 mm), restraints shall be provided for drain pipes at all changes in direction and at all changes in diameter greater than two pipe sizes. Braces, blocks, rodding and other suitable methods as specified by coupling manufacturer shall be utilized.
In buildings more than 150 ft (45.75 m) in height, all vertical lines of piping shall be provided with swing sections or traverse joints or other device which shall absorb the strains or stresses due to the expansion and contraction or vibration of the vertical pipe lines.
Piping bundles for manifold systems shall be supported in accordance with Table 18-29-308.5. Support at changes in direction shall be in accordance with the manufacturer's instructions. Where hot water piping is bundled with cold water piping, hot water piping shall be insulated in accordance with Section 18-29-607.5.
(Amend Coun. J. 10-14-21, p. 37722, Art. III, § 18)