18-29-312.7 Forced sewer test.
   Forced sewer tests shall consist of plugging the end of the building sewer at the last downstream structure before the public main and applying a pressure of 5 psi (34.5 kPa) greater than the pump rating, and maintaining such pressure for 15 minutes.
18-29-312.8 Storm drainage system test.
   Storm drain systems within a building shall be tested by water or air in accordance with Section 18-29-312.2.
18-29-312.9 Cross connection control device inspections.
   The department of water management shall inspect backflow prevention assemblies to determine proper installation including testing by a licensed Cross Connection Control Device Inspector. Reduced pressure principle backflow preventer assemblies, double check- valve assemblies, double-detector check-valve assemblies and pressure vacuum breaker assemblies shall be tested at minimum, annually, the results of annual tests shall be reported within 30 days of tests to the department of water management. In the event of test failure, immediate notification must be made to the department of water management and remedial action taken to prevent the contamination of the potable water supply. The testing procedure shall be performed in accordance with one of the following standards:
   ASSE 5010-1013-1, Sections 1 and 2
   ASSE 5010-1015-1, Sections 1 and 2
   ASSE 5010-1015-2
   ASSE 5010-1015-3, Sections 1 and 2
   ASSE 5010-1015-4, Sections 1 and 2
   ASSE 5010-1020-1, Sections 1 and 2
   ASSE 5010-1047-1, Sections 1, 2, 3 and 4
   ASSE 5010-1048-1, Sections 1, 2, 3 and 4
   ASSE 5010-1048-2
   ASSE 5010-1048-3, Sections 1, 2, 3 and 4
   ASSE 5010-1048-4, Sections 1, 2, 3 and 4
   CSA B64.1.
(Amend Coun. J. 3-27-02, p. 82090, § 3; Amend Coun. J. 11-8-12, p. 38872, § 334)
18-29-313 Equipment Efficiencies.
18-29-313.1 General.
   Equipment efficiencies shall be in accordance with the Chicago Energy Conservation Code.
(Added Coun. J. 10-14-21, p. 37722, Art. III, § 23)
18-29-314 Condensate Disposal.