1001.3.1.4 (10.3.1.4) Erosion and Sedimentation Control (ESC). Develop and implement an ESC plan for all construction activities. Regardless of the size of the site, the ESC plan shall conform to the erosion and sediment control requirements of the most current version of the IDEQ, IPDES Construction General Permit for Discharge Activities. All projects must schedule and pass an ESC Site Preparation Inspection at the start of the project and an ESC Site Final Inspection prior to a Certificate of Occupancy being granted.
(Ord. 9-23, 3-7-2023)