701.3.4 (7.3.4) Automated Demand Response (Optional). When chosen to be complied with, building projects may contain automatic control systems that have the capability to reduce building equipment loads to lower electric peak demand of the building.
The building controls may be designed with automated demand-response (DR) infrastructure capable of receiving DR requests from the utility, electrical system operator, or third-party DR program provider and automatically implementing load adjustments to the HVAC and lighting systems. Consult with local utility company for any possible eligibility requirements.
(Ord. 9-23, 3-7-2023)
701.4.1.1 (7.4.1.1) On-Site Renewable Energy Systems (Optional). When chosen to be complied with, building projects shall comply with either the Standard Renewables Approach in Section 701.4.1.1.1 (7.4.1.1.1) or the Alternate Renewables Approach in Section 701.4.1.1.2 (7.4.1.1.2). When complied with, this can be considered as equivalency to a Renewable Energy EA Credit in Normative Appendix E, Table E101.1.
(Ord. 9-23, 3-7-2023)
Amend exception 2, of section 801.3.1.8 (8.3.1.8) as follows:
2. Entrances that employ an entryway floor system that is not less than 4 ft. (1.3 m) in length to provide access to spaces that are less than 3,000 ft2 (300 m2) in area.