901.3.1.3 (9.3.1.3) Construction Material and Waste Management Plan. A Construction Material and Waste Management Plan shall be developed and implemented to reuse, recycle, or salvage construction materials and waste. This plan can be submitted upon application for a permit, or can be requested to be a deferred submittal, however, the plan must be submitted for review and approval prior to the first inspection on the construction site. The Construction Material and Waste Management Plan shall include the following:
a. Identify the construction and demolition waste materials expected to be diverted from disposal in landfill by reuse, recycling, manufacturer's reclamation, or salvage for future use, donation, or sale.
b. The percentage of materials to be diverted shall be specified and shall be calculated by weight or volume, but not both.
c. The location for collection, separation and storage of recyclable construction waste shall be indicated.
d. Determine whether construction and demolition waste materials are to be source-separated or comingled.
e. Identify service providers and designate destination facilities for construction and demolition waste materials generated at the job site.
f. Identify the average diversion rate for facilities that accept or process comingled construction and demolition materials. Separate average percentages shall be included for those materials collected by construction and demolition materials processing facilities that end up as alternative daily cover and incineration.
Demolition materials and waste shall include from existing buildings or portions of existing buildings. Construction materials and waste shall include all materials delivered to the site and intended for installation prior to the issuance of the certificate of occupancy, including related packaging and delivery materials.
(Ord. 9-23, 3-7-2023)