2104.10 Substitution.
Mortar shall not be substituted for grout where grout is specified on the construction documents.
2105.1 General.
A quality assurance program shall be used to ensure that the constructed masonry is in compliance with the approved construction documents.
The quality assurance program shall comply with the inspection and testing requirements of Chapter 17 and TMS 602.
2105.2 Submittals.
Submittals required by Article 1.5 of TMS 602 shall be sent to the applicant of record for review prior to use of the materials or methods of construction. In addition the contractor shall submit a Material Storage and Protection Plan.
2106.1 Seismic design requirements for masonry.
Masonry structures and components shall comply with the requirements in Chapter 7 of TMS 402 depending on the structure's seismic design category as determined in Section 1613 of this code. All masonry walls, unless isolated on three edges from in-plane motion of the basic structural systems, shall be considered to be part of the seismic-force-resisting system.
2106.1.1 Non-participating masonry walls.
Masonry walls that are not part of the lateral force resisting system shall be isolated from the structure so that the vertical and lateral forces are not imparted to these elements. Isolation joints and connectors between these elements and the structure shall be designed to accommodate the design story drift.