170.30   WIND ENERGY CONVERSION SYSTEMS.
1.   Purpose. The purpose of this section is to allow and encourage the safe, effective and efficient use of small wind energy systems; identify locations in areas of the City which would be least adversely impacted by the visual, aesthetic, and safety implications of their siting; and enhance the ability of the providers of wind energy services to provide such services to the community quickly, efficiently, and effectively.
2.   General Regulations.
A.   General: wind energy conversion systems shall be allowed as a special use accessory to a permitted use in all zoning districts other than residential zoning districts.
B.   Prohibited: commercial wind energy conversion systems are prohibited within the City and the Two-Mile 28-E Agreement Area.
C.   Number of systems per property: no property shall contain more than one wind energy conversion system.
D.   Permit required: all wind energy conversion systems require a special use permit to be obtained from the Board of Adjustment prior to site grading and installation. The Board of Adjustment can revoke a special permit at any time if the requirements set forth in this ordinance and/or any conditions imposed by the Board of Adjustment are not met. The Board of Adjustment will revoke the special use permit of an abandoned wind energy conversion system.
E.   Insurance: the owner/operator of a wind energy conversion system unit must demonstrate adequate liability insurance.
F.   FAA Regulations: wind energy conversion systems must comply with applicable FAA regulations, including any necessary approvals for installations close to airports. The applicant has the responsibility of determining applicable FAA regulations and must provide evidence of securing the necessary approvals.
G.   Maintenance: all wind energy conversion systems shall be properly maintained in operational condition at all times, subject to reasonable maintenance and repair outages. The owner of any wind energy conversion system deemed unsafe by the zoning official or his/her designee shall repair the structure to meet all federal, state and local safety standards or remove it within six (6) months.
3.   Bulk Regulations:
A.   Minimum Lot Size: two (2) acre minimum lot size required for any tower mounted wind energy conversion systems.
B.   Minimum Setback Requirements: all wind energy conversion systems shall require a setback of one hundred ten percent (110%) of the total system height from any property line.
C.   Maximum Height: the maximum height for wind energy conversion system is eighty (80) feet.
D.   Number of Systems Allowed: no more than one (1) wind energy system may be placed on any parcel.
E.   Location:
(1)   Tower mounted wind energy conversion systems shall only be located outside of any minimum building setback requirements.
(2)   No part of a wind energy conversion system shall be located within or over drainage, utility or other established easements, or on or over property lines.
(3)   A wind energy conversion system shall be in compliance with guidelines of the Federal Aviation Administration (FAA) regulations.
(4)   No wind energy conversion system shall be constructed within twenty (20) feet laterally of an overhead electrical power line (excluding secondary electrical service lines or service drops). The setback from underground electric distribution lines shall be at least five (5) feet.
(5)   No wind energy conversion system shall be located in a residential zoning district.
(6)   No roof mounted wind energy conversion system will be allowed.
4.   Minimum System Design Standards. The following standards are required of all wind energy conversion systems and shall be deemed to be conditions of approval for every wind energy system.
A.   Color: the wind energy conversion system shall be white or light gray in color. Other neutral colors may be allowed at the discretion of the Board of Adjustment. The surface of the structure shall be non-reflective.
B.   Lighting: no lights shall be installed on the tower, unless required by the Federal Aviation Administration (FAA).
C.   Signs: One sign, limited to four (4) square feet, shall be posted at or near the base of the tower. The sign shall include a notice of no trespassing, a warning of high voltage, and the phone number to the property owner/operator to call in case of emergency. Such sign shall be directly visible from any external fencing and/or landscaping. Brand names or advertising associated with any installation shall not be visible from any public right-of-way.
D.   Clearance of Blade Above Ground: no portion of the tower mounted wind energy conversion system shall extend within thirty (30) feet of the ground. No blades may extend over parking areas, driveways or sidewalks.
E.   Installation: installation must be done by a qualified professional and according to manufacturer’s recommendations.
F.   Noise: the wind energy conversion system shall not exceed 65 decibels, except during short term events such as severe wind storms and utility outages. Maximum sound pressures will be measured from the closest point on the closest property line.
G.   Use of Electricity Generated: a wind energy conversion system shall be used exclusively to supply electrical power for onsite consumption, except that when a parcel on which a wind energy conversion system is installed also receives electrical power supplied by a utility company, excess electrical power generated by the wind energy system and not presently needed for onsite use may be used by the utility company in accordance with Section 199, Chapter 15.11(5) of the Iowa Administrative Code.
H.   Automatic Over speed Controls: all wind energy conversion systems shall be equipped with manual and automatic over-speed controls to limit the blade rotation speed to within the design limits of the wind energy conversion system.
I.   Electromagnetic Interference: all blades shall be constructed of a nonmetallic substance. No wind energy conversion system shall be installed in any location where its proximity with existing fixed broadcast, retransmission, or reception antenna for radio, television, or wireless phone or other personal communication systems would produce electromagnetic interference with signal transmission or reception. No wind energy conversion system shall be installed in any location along the major axis of an existing microwave communications link where its operation is likely to produce electromagnetic interference in the link’s operation.
J.   Interconnection: the wind energy conversion system, if interconnected to a utility system, shall meet the requirements for interconnection and operation as set forth by the utility and the Iowa Utilities Board.
K.   Wind Access Easements: the enactment of this section does not constitute the granting of an easement by the City. The owner/operator shall provide covenants, easements, or similar documentation to assure sufficient wind to operate the wind energy conversion system unless adequate accessibility to the wind is provided by the site.
L.   Shadow Flicker: a shadow flicker model demonstrates that shadow flicker shall not fall on, or in, any existing residential structure. Shadow flicker expected to fall on a roadway or a portion of residentially zoned parcel may be acceptable if the flicker does not exceed thirty (30) hours per year; and the flicker will fall more than one hundred (100) feet from an existing residence; or the traffic volumes are less than five hundred (500) vehicles per day on the roadway. The shadow flicker model shall:
(1)   Map and describe within a one thousand (1,000) foot radius of the proposed dispersed wind energy system the topography, existing residences and location of their windows, locations of other structures, wind speeds and directions, existing vegetation and roadways. The model shall represent the most probable scenarios of wind constancy, sunshine constancy, and wind directions and speed;
(2)   Calculate the locations of shadow flicker caused by the proposed project and the expected durations of the flicker at these locations, calculate the total number of hours per year of flicker at all locations;
(3)   Identify problem areas where shadow flicker will interfere with existing or future residences and roadways and describe proposed mitigation measures, including, but not limited to, a change in sitting of the wind energy conversion system, a change in the operation of the wind energy conversion system, or grading or landscaping mitigation measures.
M.   Appearance: the property owner of any wind energy system shall maintain such system in a safe and attractive manner, including replacement of defective parts, painting, cleaning, and other acts that may be required for the maintenance and upkeep of the function and appearance of such a system. The owner shall maintain the ground upon which the system is located in an orderly manner, such that is free of debris, tall grass and weeds, and any structures remain quality in appearance.
5.   Abandonment. Any wind energy system that is not operated for a period of one hundred eighty (180) consecutive days shall be considered abandoned and shall constitute a nuisance. Within the next 180 days, after notice from the City, the owner shall reactivate the tower or it shall be dismantled and removed at the owner’s expense. Removal of the system includes the entire structure including foundations, transmission equipment and fencing from the property. If the abandoned wind energy system is not removed in the specified amount of time, the City may remove it and recover its costs from the wind energy conversion system owner or owner of the ground upon which it is located.
6.   New Technologies. Should new technology present itself after construction that is more effective, efficient, and economical, the owner may petition the City to allow the upgrade, provided that the upgrade does not alter the conditions set forth in this chapter.
7.   Liability and Damages. The owner/operator of a wind energy conversion system must demonstrate adequate liability insurance. Upon the granting of a permit, applicant shall assume full responsibility for any and all damages, claims, expenses, liabilities, judgments and costs of any kind, including reasonable attorney’s fees related to or caused by the erection, location, use, or removal of a facility, whether on public or private property, and shall agree to hold the City harmless, indemnify and defend it from all such liabilities incurred or judgments entered against it as a result of the erection, location, use or removal of the facility.
8.   Engineer Certification. Applications for wind energy conversion systems shall be accompanied by standard drawings of the wind turbine structure, including the tower, base, and footings. An engineering analysis of the tower showing compliance with the applicable regulations and certified by a licensed professional engineer shall also be submitted.
9.   Utility Notification. A wind energy conversion system shall not be installed until evidence has been given that the utility company has been informed of the customer’s intent to install an interconnected customer-owned generator.
10.   Application and Approval Requirements. Applications for a special use permit shall be submitted with the following information:
A.   A properly completed and signed application.
B.   A statement from the applicant that the wind energy conversion system will be installed in compliance with manufacturer’s specifications, and a copy of the manufacturer’s specifications.
C.   A statement indicating what hazardous materials will be used or stored on the site and how those materials will be stored.
D.   A description of the wind energy conversion system’s height and design, including a cross section, elevation, and diagram of how the wind energy conversion system will be anchored to the ground, prepared by a professional engineer licensed in the State of Iowa.
E.   A site plan including the following information:
(1)   Legal description of the property
(2)   Parcel boundaries
(3)   Existing buildings
(4)   Easements
(5)   Fencing
(6)   Proposed location of wind energy conversion system
(7)   Setbacks
(8)   Travel ways
(9)   Overhead utility lines
(10)    Contour map with contours at intervals of two feet, if the general slope is less than ten (10) percent, and at vertical intervals of five feet if the general slope is greater than ten (10) percent.
(11)    If connection to the publicly regulated utility grid is proposed, a copy of the contract between applicant and utility verifying the proposed connection is acceptable, and/or other evidence making clear that the utility is aware of the proposed connection and finds it acceptable.
(12)    Shadow flicker model.
F.   The City may require that the application and site plan be reviewed by a City Engineer before the Board of Adjustment schedules a hearing on the application for a special use permit.
11.   Accessory Use. A wind energy conversion system shall only be allowed as an accessory use to a permitted principal use.