Loading...
The city shall keep on file all copies of permits issued under this subchapter and to inspect from time to time all pavement, or other street surfacing, disturbed pursuant to those permits. If the pavement or surfacing is not restored and maintained as nearly as possible to the original condition, notice shall be given the permittee, who shall put the pavement or surfacing in good condition within three days. If the permittee fails after notice given to restore and maintain the pavement or the surface thereof, the city may make the necessary repairs and the permittee shall pay the costs thereof, and until the costs are paid, no other permit shall be issued to him or her or to any person in his or her behalf.
(1992 Code, § 38-58) (Ord. 104-99, passed 10-14-1999)
No person shall make or cause to be made any excavation on any lot adjacent to any street, alley, public ground or traveled road, or roadway, except the excavations be securely guarded so as to prevent the injury of any person or animal passing upon or along the street, alley, ground or road.
(1992 Code, § 38-59) (Ord. 104-99, passed 10-14-1999)
PERMIT REQUIRED
No person shall make or cause to be made any excavation in or under any street, parking, sidewalk, alley or public ground or remove any earth, soil, paving, gravel or material therefrom without first having obtained a permit for the work therefor from the city
(1992 Code, § 38-60) (Ord. 104-99, passed 10-14-1999) Penalty, see § 10.999
The following fees shall be charged for permits. The city shall compute the amount of the fee which shall be paid to the city. No fee provided for by this section shall be charged for work for city purposes by departments of the city.
Permit | Fee |
Permit | Fee |
Construction permit (installation of public improvements; including street grading, curb and gutter, roadway subbase, base and surface, drainage and flood control, water, and sanitary sewer in proposed subdivisions) | $50 |
Excavation and grading permit (grading outside the street right-of-way in proposed subdivisions and individual lots as defined by the Uniform Building Code) | $50 |
Other fees: | |
Permanent repair during winter when weather permits usage of permanent patch | |
0–16 square feet | $180 |
For each additional square foot | $8 |
Replacing asphaltic surface cuts, permanent repair when hot asphalt is available | |
0–16 square feet | $140 |
For each additional square foot | $4 |
A mobilization charge of $50 will be assessed if the patch area is not properly prepared and the city patch crew has been requested to the site. | |
The city reserves the right to require the contractor to provide their own qualified asphalt contractor for patching of the street. All expenses incurred are to be paid by the contractor. | |
Sewer, water and sump pump permit (installation, removal, repair or maintenance of sanitary sewer services, water services, storm sewer services and sump pump services) | $50 |
Sidewalk and driveway permit (new access points from private property to city streets including construction or repair of driveways and sidewalks. Any person who repairs or replaces a sidewalk within the right-of-way and in front of or along a residential property owned by him or her shall be exempt from the sidewalk and driveway permit fee.) | $15 |
Street cut permit (installation, removal, repair or maintenance of private facilities other than sanitary sewer, water and storm sewer services in the public right-of-way or easement) | $30 |
Sump pump collection system permit (connection to an existing collection system not constructed by the developer of lot connecting to the system) | $454 |
Sump pump connection permit (installation of sump pump discharge line from building to storm sewer or collection system) | $10 |
Contractors and utility companies will be billed monthly, payable within 30 days after the billing date. | |
(1992 Code, § 38-62) (Ord. 104-99, passed 10-14-1999; Ord. 106-00, passed 12-12-2000; Ord. 13-05, passed 2-14-2005; Ord. 91-06, passed 7-24-2006; Ord. 91-24, passed 10-8-2024)