Within thirty-five days from the date of preliminary/final plan submission, the Planning Commission shall either approve the submitted plan, approve a modified plan or disapprove the plan, unless the applicant consents to an extension of time. If the Planning Commission disapproves the plans, the Planning Commission shall state the reason for disapproval. Failure of the Planning Commission to approve the submitted plan, approve a modified plan or disapprove the plan, within thirty-five days from the date of submission of the plans, shall be deemed an approval of the plans.
(Ord. 2001-4. Passed 1-16-01.)