If a development project requires concurrent processing of multiple permits, or of one or more permits and one or more other discretionary approvals by the city, and the permit coordination officer determines that one or more of the applications for such a permit or approval are incomplete and requests further information, the applicant shall provide the requested information for each such application to the filing officer within thirty (30) calendar days after the request, unless a different time period has been specified by the permit coordination officer or mutually agreed upon between the applicant and the permit coordination officer.
The provisions of this chapter applicable to a development project for which only one permit is required shall otherwise apply to a development project requiring multiple permits or a combination of one or more permits and one or more other discretionary approvals by the city.
(Ord. 2312 §19)