Excavated materials removed during grading operations shall be handled in accordance with the following methods:
A. Stockpiling sufficient topsoil on the site if necessary for use on areas to be revegetated.
B. Locating stockpiled soil so that it will not become a source for off-site sediment damage.
C. Promptly backfilling and compacting stockpiled soil into trenches and pits to reduce the risk of erosion.
D. Applying mulch or other protective coverings on stockpiled material which will be exposed through the winter season.
E. Excavated material not to be used at the site shall be disposed of in a manner and at a location approved by the building official.
(Res. No. 103 90-91 §1 (part), Ord. No. 2540 §11, Ord. No. 2577 11-15-22 §11)