A. Wireless telecommunications facilities permits shall be acted upon by the director. Wireless telecommunications facilities shall be issued when all of the following requirements are met.
1. The facility meets the development standards set forth in this chapter.
2. The facility will not generate EMF/RF radiation in excess of the FCC adopted standards for human exposure.
3. If the facility is a new telecommunications tower, it does not exceed 100 feet in height, or 65 feet in height if located in the AM zoning district.
4. The facility does not encroach into navigable airspace as defined by Part 77 of Title 14 of the Code of Federal Regulations.
5. If the facility is a new telecommunications tower, that the facility, and construction thereof, will avoid all sensitive habitats and rare, threatened and endangered species which may be on the site.
B. The director shall act on all applications for wireless telecommunications facilities permits within 90 days of the submission of a completed application.
` C. Wireless telecommunications facilities permits shall be approved or denied in writing. All denials shall state the reasons for the denial. Reasons for denial shall be limited to a finding by the director that one of the requirements for issuance, as set forth in A., above, has not been met.
(Ord. 2205, Ord. 2364 §404, Ord. 2519 §37)