A. Notice of Completion. Where the project involves a state trustee or responsible agency, the director shall file a notice of completion in accordance with the State Guidelines with the State Clearinghouse, along with ten (10) copies of the draft EIR. The State Clearinghouse will distribute the draft EIR to applicable state agencies.
B. Notice of Availability.
1. The director shall provide public notice of availability within a reasonable time following issuance of the notice of completion.
2. Notices shall contain the information and be in a form determined by the director.
3. Notices shall be sent to:
a. Parties sent the notice of preparation in the manner specified for notices of preparation above;
b. Individuals and organizations requesting such notice.
4. Additionally, notice shall be given by at least one of the following procedures:
a. Publication, no fewer times than required by Section 6061 of the Government Code, by the public agency in a newspaper of general circulation in the area affected by the proposed project; or
b. Posting of the notice by the public agency on- and off-site in the area where the project is to be located; or
c. Direct mailing to the owners and occupants of contiguous property as shown on the latest equalized assessment roll.
5. Additional notification requirements apply to projects involving the burning of municipal wastes, hazardous wastes, and refuse-derived fuels pursuant to CEQA.
(Ord. 2067, Ord. 2364 §48)