The building official shall review each grading permit application and any grading plans and specifications, soils engineering report, engineering geology report or other data and information required to be submitted therewith and shall approve and issue a permit to the applicant authorizing the grading work described in the permit, upon determining that:
A. The application and any grading plans and specifications, soils engineering report, engineering geology report or other data and information required to be submitted therewith comply with this chapter and the grading standards adopted by Chapter 16.26;
B. Any required environmental review is complete and any mitigation measures resulting from it are included in the permit;
C. All required permit and grading plan check fees have been paid; and
D. All other requirements of this code and other applicable laws or regulations have been met.
(Ord. 2312 §25)