14A-4-413.9.1 Extension of time or reinstatement.
For each permit, the building official may grant up to two extensions of time or reinstatements, for periods of 180 days each, prior to the start of construction activities, and up to four extensions of time or reinstatements, for periods of 180 days each, after the start of construction activities, provided that the cumulative duration of extensions of time and reinstatements for the same permit or group of related permits may not exceed 720 days. The building official must collect a fee as provided in Table 14A-12-1204.1 before granting an extension of time or reinstatement.
(Amend Coun. J. 10-7-20, p. 21791, Art. I, § 18)