A permit for plumbing work must be obtained in accordance with Section 18-29-106 of the Municipal Code. A permit application for plumbing work may be submitted as part of a general building permit application that clearly identifies the scope of plumbing work to be performed or as a separate permit application.
A permit must be obtained before relocating an existing building or structure, either on the same lot or from one lot to another. The permit application must be accompanied by plans demonstrating compliance with Chapter 14 of the Chicago Building Rehabilitation Code.
A permit may not be issued for the relocation of an existing building or structure that has been damaged by fire, decay, or otherwise to a new lot where repairs necessary to bring the damaged structure into compliance with the Chicago Construction Codes would exceed 50 percent of the value of the damaged structure.
In addition to any permit or authorization required for work on or over the public way, a separate permit must be obtained from the building official for scaffolding that meets either of the following criteria:
1. Erected more than 40 feet (12.2 m) above adjoining grade on a site within the fire limits, as defined in Appendix D to the Chicago Building Code.
2. Erected more than 80 feet (24.4 m) above adjoining grade.
The permit for scaffolding must be separate from any permit required for construction, demolition, or rehabilitation work.
Application for a scaffolding permit must be submitted on a form provided by the building official for this purpose. The application must clearly describe all scaffolding to be erected or used under the permit. The applicant must provide such information on the application as the building official may require, including the name of the owner, the address of the building, the periods of time during which the scaffolding work will take place, the nature of the scaffolding work to be done, the type and size of the scaffolding to be used, and a telephone number that will enable the City to contact the applicant at all times in case of emergency. The application must include a signed statement by the applicant attesting that the applicant is familiar with all laws, rules, and standards applicable to scaffolding proposed in the application to be erected and used.