The following types of service equipment shall not be operated until the department issues a certificate of compliance after submission of a satisfactory report of inspection and testing of such equipment in accordance with this code and all required submittal documents:
1. Air-conditioning, ventilation and exhaust systems
2. Elevators, escalators, moving walkways and dumbwaiters
3. Fuel burning and fuel-oil storage equipment
4. Refrigeration systems
5. Heating systems
6. Boilers.
Exception: A certificate of compliance shall not be required in connection with work specifically exempted from permit requirements in accordance with this code or department rules.
The department may refuse to issue a letter of completion or certificate of occupancy pending payment of all outstanding fines or civil penalties imposed for violations of this code, the 1968 building code or other laws enforced by the department at the same building.
For all work where approval is sought based upon section 28-116.6, the approved fabricator shall submit a certificate of intent to fabricate such work to the department identifying the work to be performed as an approved fabricator, and that such work shall be performed in accordance with the approved construction documents, referenced standards and applicable provisions of law and for which site the work is being fabricated prior to fabricating any items for such project.
(Am. L.L. 2021/126, 11/7/2021, eff. 11/7/2022)
Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.
For all fabricated items, the approved fabricator shall submit a certificate of compliance to the department stating that the work was performed in accordance with the approved construction documents, referenced standards and applicable provisions of law.
(Am. L.L. 2021/126, 11/7/2021, eff. 11/7/2022)
Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.
The department shall not issue a certificate of occupancy or letter of completion with respect to a building or premises that is part of a covered development project unless the applicant submits proof that the department of environmental protection has issued a stormwater maintenance permit for any post-construction stormwater management facilities serving such building or premises.
(L.L. 2017/097, 5/30/2017, eff. 6/1/2019)
It shall be unlawful to use or occupy any building or space, including an outdoor space, as a place of assembly without a certificate of operation issued by the commissioner. An application for a certificate of operation shall be made to the department in such form and containing such information as the commissioner shall provide. The department shall inspect every place of assembly space prior to the issuance of a certificate of operation. The commissioner shall not issue a certificate of operation unless the department determines that the space conforms substantially to the approved construction documents and to this code or the 1968 building code as applicable and that the certificate of occupancy authorizes such use. A certificate of operation shall not be issued to a place of assembly providing seating or other moveable furnishings unless the commissioner approves a plan conforming to this code or the 1968 building code as applicable and the rules of the department. Seating and other moveable furnishings shall be maintained at all times during occupancy in accordance with the approved plan. Any amendment of such plan shall be subject to the prior approval of the commissioner.
The certificate of operation shall contain the place of assembly certificate number, the number of persons who may legally occupy the space and any other information that the commissioner may determine. Such certificate of operation shall be framed and mounted in a location that is conspicuously visible to a person entering the space. For the purposes of this article a department issued place of assembly permit or place of assembly certificate of operation shall be valid until its expiration, at which time a new place of assembly certificate of operation shall be required in accordance with the provisions of this article and with the filing requirements of the department.