It shall be the duty of the permit holder to notify the department or the person or entity designated to perform the inspection when work requiring inspection is ready to be inspected. It shall be the duty of the permit holder to provide access to and means for inspection of such work for any inspections that are required by this code.
Upon submission of a satisfactory report of final inspection and all required submittal documents, the department shall document the sign-off of the project and issue a letter of completion, or, if applicable, a certificate of occupancy for the work. The owner shall take all necessary steps required by the department for the issuance of such letter of completion or certificate of occupancy within one year following the expiration of the last permit.
(Am. L.L. 2021/126, 11/7/2021, eff. 11/7/2022)
Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.
The following types of service equipment shall not be operated until the department issues a certificate of compliance after submission of a satisfactory report of inspection and testing of such equipment in accordance with this code and all required submittal documents:
1. Air-conditioning, ventilation and exhaust systems
2. Elevators, escalators, moving walkways and dumbwaiters
3. Fuel burning and fuel-oil storage equipment
4. Refrigeration systems
5. Heating systems
6. Boilers.
Exception: A certificate of compliance shall not be required in connection with work specifically exempted from permit requirements in accordance with this code or department rules.
The department may refuse to issue a letter of completion or certificate of occupancy pending payment of all outstanding fines or civil penalties imposed for violations of this code, the 1968 building code or other laws enforced by the department at the same building.
For all work where approval is sought based upon section 28-116.6, the approved fabricator shall submit a certificate of intent to fabricate such work to the department identifying the work to be performed as an approved fabricator, and that such work shall be performed in accordance with the approved construction documents, referenced standards and applicable provisions of law and for which site the work is being fabricated prior to fabricating any items for such project.
(Am. L.L. 2021/126, 11/7/2021, eff. 11/7/2022)