Beginning in 2022, on or before October 1 of each year, the building official must determine the percentage change in the Consumer Price Index for All Urban Consumers, US City Average (CPI-U) from January 2021 to January of the present year and prepare fee schedules, based on Tables 14A-12-1204.3(1) through 14A-12-1204.3(6), with monetary values in the bodies of the table adjusted in proportion to the change in CPI-U. The building official may round minimum fees to the nearest $50 increment. Fee schedules prepared by the building official in accordance with this section and published on the City's public web site are effective on January 1 of the succeeding year.
(Added Coun. J. 10-27-21, p. 40504, Art. IV, § 4)
Where a penalty must be added to the permit fee in accordance with Section 14A-4-412.4 it must be assessed in accordance with Table 14A-12-1204.4.
Where the stop work order was issued because work was done by a person lacking a trade license required under the Municipal Code or by a person required by the Municipal Code to be listed on the permit application who was not listed, the penalty is the amount provided in Table 14A-12-1204.4 based on the amount of the regular permit fee plus $1,000.
Regular Permit Fee
|
Reason | Penalty Amount
|
Any amount | Work without a required permit or beyond scope of issued permit, or performed by a person who is required to be licensed or listed on the permit application and is not | 200% of regular permit fee |
Work pursuant to a permit but that is unsafe or contrary to the Chicago Construction Codes or Chicago Zoning Ordinance | 100% of regular permit fee |
(Amend Coun. J. 12-14-22, p. 58278, Art. II, § 16)
Fees applicable to the provisions of Chapter 5 are as provided in Table 14A-12-1205.1.
Section
|
Description
|
Amount
|
Reinspection fee (per inspection) | $100 | |
Extra inspection fee (per inspector, per hour or fractional hour) Minimum fee | $100 $250 |
Fees applicable to the provisions of Chapter 6 are as provided in Table 14A-12-1206.1.
Section
|
Description
|
Amount
|
Section
|
Description
|
Amount
|
Per reinspection | $100 | |
Late payment penalty (per each 30 days past due but not to exceed 100 percent of the assessed fee) | $5 | |
Periodic inspection - Group A occupancy | ||
First 25,000 square feet (or fraction thereof) | $120 | |
Each additional 25,000 square feet (or fraction thereof) | $60 | |
Periodic inspection - other than Group A occupancy | ||
First 25,000 square feet (or fraction thereof) | $80 | |
Each additional 25,000 square feet (or fraction thereof) | $40 | |
Filing fee | $75 | |
Re-review fee for deficient report | $75 | |
Filing fee | $25 | |
Re-review fee for deficient report | $25 | |
Filing fee | $75 | |
Re-review fee for deficient report | $75 | |
Filing fee | $75 | |
Re-review fee for deficient report | $75 | |
Per curtain | $100 | |
Per tank (including support structure) | $150 | |
Elevator, vertical reciprocating conveyor, or manlift | ||
10 stories or less a | $105 | |
11 to 20 stories a | $125 | |
21 to 30 stories a | $140 | |
Over 30 stories a | $155 | |
Escalator or moving walk | $75 | |
Movable stage or orchestra floor | $125 | |
Platform lift | $75 | |
Hinged platform lift for trucks or loading docks | $45 | |
Material lifts | $105 | |
Platform lift or stairway lift | $50 | |
Mechanical amusement riding device | ||
Coin-operated (annual permit required) | n/a | |
Other than coin-operated | $100 | |
Any other conveyance device | $75 | |
Per 1,000 cubic feet per minute of required supply and exhaust (minimum fee: $50) | $5 | |
Per generator or compressor b | ||
Capacity of 3 tons or less | $50 | |
Capacity over 3 tons and not over 30 tons | $60 | |
Capacity over 30 tons and not over 100 tons | $70 | |
Capacity over 100 tons and not over 1,000 tons | $80 | |
Capacity over 1,000 tons | $100 | |
Per boiler | ||
Capacity over 288,000 and not over 2.4 million BTU/hr | $50 | |
Capacity over 2.4 million and not over 6 million BTU/hr | $75 | |
Capacity over 6 million BTU/hr | $85 | |
Per unfired pressure vessel | ||
Diameter under 18 inches | $45 | |
Diameter between 18 and 36 inches | $55 | |
Diameter of 36 inches or more | $65 | |
Signs | See Ch. 13-20 | |
a. Skip stops must be included when determining number of stories.
b. Compressor capacity is based on the applicable Air-Conditioning and Refrigeration Institute published rating for the equipment involved.