R110.4 Temporary occupancy. If the building official finds that no substantial hazard will result from occupancy of a building or portion thereof before the same is completed, a Temporary Certificate of Occupancy may be issued for the use of a portion or portions of a building or structure prior to the completion of the entire building or structure. A temporary occupancy may be issued for up to 90 calendar days. Multiple time extensions of a maximum of 90 calendar days each may be granted when requested in writing to the building official when a reasonable effort is demonstrated by the permit holder. In no case shall a temporary occupancy extend beyond two (2) years, unless the building official finds extenuating circumstances.
(Ord. 40-20, 12-1-2020, eff. 1-1-2021)