The building official, after receiving notification from the applicant that the project is ready for inspection, shall conduct the inspections in sections 91.1.110.3.1 through 91.1.110.3.9.
(Added by Ord. No. 10146 (N.S.), effective 5-13-11; repealed and reenacted by Ord. No. 10464 (N.S.), effective 4-14-17; repealed and adopted by Ord. No. 10651 (N.S.), effective 2-28-20; repealed and adopted by Ord. No. 10829 (N.S.), effective 3-10-23)
Footing and foundation inspections shall be made after excavations for footings are complete and any required reinforcing steel and anchoring hardware are in place, but before concrete is poured. For concrete foundations, any required forms shall be in place prior to inspection. Materials for the foundation shall be on the job, except where concrete is ready mixed in accordance with ASTM C 94, the concrete need not be on the job.
(Added by Ord. No. 10146 (N.S.), effective 5-13-11; repealed and reenacted by Ord. No. 10464 (N.S.), effective 4-14-17; repealed and adopted by Ord. No. 10651 (N.S.), effective 2-28-20; repealed and adopted by Ord. No. 10829 (N.S.), effective 3-10-23)
Concrete slab and under-floor inspections shall be made after in-slab or under-floor reinforcing steel and building service equipment, conduit, piping accessories and other ancillary equipment items are in place, but before any concrete is placed or floor sheathing installed, including the subfloor.
(Added by Ord. No. 10146 (N.S.), effective 5-13-11; repealed and reenacted by Ord. No. 10464 (N.S.), effective 4-14-17; repealed and adopted by Ord. No. 10651 (N.S.), effective 2-28-20; repealed and adopted by Ord. No. 10829 (N.S.), effective 3-10-23)
In flood hazard areas, upon placement of the lowest floor, including the basement, and prior to further vertical construction, the elevation certification required in Title 8, Division 11, of the County of San Diego Code of Regulatory Ordinances shall be submitted to the building official.
(Added by Ord. No. 10146 (N.S.), effective 5-13-11; repealed and reenacted by Ord. No. 10464 (N.S.), effective 4-14-17; repealed and adopted by Ord. No. 10651 (N.S.), effective 2-28-20; repealed and adopted by Ord. No. 10829 (N.S.), effective 3-10-23)
Framing inspections shall be made after the roof deck or sheathing, all framing, fireblocking and bracing are in place and pipes, chimneys and vents to be concealed are complete and the rough electrical, plumbing, heating wires, pipes and ducts are approved.
(Added by Ord. No. 10146 (N.S.), effective 5-13-11; repealed and reenacted by Ord. No. 10464 (N.S.), effective 4-14-17; repealed and adopted by Ord. No. 10651 (N.S.), effective 2-28-20; repealed and adopted by Ord. No. 10829 (N.S.), effective 3-10-23)
Lath and gypsum board inspections shall be made after lathing and gypsum board, interior and exterior, is in place, but before any plastering is applied or gypsum board joints and fasteners are taped and finished.
(Added by Ord. No. 10146 (N.S.), effective 5-13-11; repealed and reenacted by Ord. No. 10464 (N.S.), effective 4-14-17; repealed and adopted by Ord. No. 10651 (N.S.), effective 2-28-20; repealed and adopted by Ord. No. 10829 (N.S.), effective 3-10-23)
Protection of joints and penetrations in fire- resistance-rated assemblies shall not be concealed from view until inspected and approved.
(Added by Ord. No. 10146 (N.S.), effective 5-13-11; repealed and reenacted by Ord. No. 10464 (N.S.), effective 4-14-17; repealed and adopted by Ord. No. 10651 (N.S.), effective 2-28-20; repealed and adopted by Ord. No. 10829 (N.S.), effective 3-10-23)