All applications for permits for work on a building having more than three dwelling units shall state (i) the total number of units in the building at the time the application is filed, (ii) the number of units occupied at the time the application is filed, and (iii) the number of units to be occupied during the course of the work. The work permit application shall be amended prior to occupancy of any units that were not initially counted as being occupied during the course of the work.
(L.L. 2017/149, 8/30/2017, eff. 12/28/2017; Am. L.L. 2021/126, 11/7/2021, eff. 11/7/2022)
Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.
All applications for permits shall include a certification by the owner of the property for which the permit is sought stating the following:
1. A statement as to whether $25,000 or more in covered arrears, that are not currently in the appeals process, are owed to the city with respect to such property;
2. A statement as to whether the owners of the property owe, in aggregate, $25,000 or more in covered arrears to the city;
3. For each owner of the property:
3.1. The person's full name and business address;
3.2. A list of properties in the city for which the person owes covered arrears to the city and, for each such property, the amount of such covered arrears owed; and
3.3. A list of properties in the city for which the person is an owner;
4. If an exception to section 28-105.1.6 applies to such owner, a description of such exception.
(L.L. 2017/160, 8/30/2017, eff. 12/28/2017; Am. L.L. 2021/126, 11/7/2021, eff. 11/7/2022)
Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.
The commissioner shall each year, in consultation with the department of finance and each other appropriate city agency, audit at least 25 percent of the statements submitted under section 28-105.5.3.
(L.L. 2017/160, 8/30/2017, eff. 12/28/2017; Am. L.L. 2021/126, 11/7/2021, eff. 11/7/2022)
Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.
Applications for permits shall be accompanied by the payment of appropriate fees as provided for in article 112.
An application for a permit shall be deemed to have been abandoned 12 months after the date of its submission, unless such application has been diligently prosecuted after rejection in whole or in part, or a permit shall have been issued except that the commissioner may, for reasonable cause, and upon payment of all reinstatement fees as provided for in this code, grant extensions of time for additional 12-month periods.