Pre-application meeting applications must be submitted to the Chief Subdivision Engineer on forms available from the County Land Use Department.
(Ord. passed 7-8-1970; Res. 09-167, passed 6-18-2009) Penalty, see § 154.999
The following information and documentation shall be required for the pre-application meeting: a complete application; a plat of survey or tax map; and a sketch plan.
(A) Application. The developer must complete a pre-application meeting application form, which may be obtained in the County Land Use Department office.
(B) Plat of survey. The developer must provide a plat of survey of the subject property, if available, or a tax map identifying the subject property.
(C) Sketch plan. The developer must provide a sketch plan that includes the following information:
(1) The proposed means of access;
(2) Surrounding land uses;
(3) All adjacent streets;
(4) A preliminary map and analysis of natural resources present on the subject property and contiguous resource area on adjacent property, including hydric soils (information may be obtained from the County Land Use Department); and
(5) A conceptual layout of the proposed subdivision overlaid on the preliminary natural resources map. The layout must show streets, lots, parks and other facilities located to protect natural resources; and the overall stormwater management concept for the project.
(Ord. passed 7-8-1970; Res. 09-167, passed 6-18-2009) Penalty, see § 154.999
Upon receipt of a complete pre-application meeting application, the Chief Subdivision Engineer must distribute copies of the application to appropriate reviewers (e.g., Road District Commissioner, utility providers, municipalities within one and one-half miles of the proposed subdivision, county staff and other affected entities). The Chief Subdivision Engineer must notify all reviewers and the applicant of the date, time and place of the scheduled pre-application meeting.
(Ord. passed 7-8-1970; Res. 09-167, passed 6-18-2009)
(A) Reviewer comments on the pre-application meeting application will be presented to the applicant at the scheduled pre-application meeting. Each reviewer will be given an opportunity to present their findings and recommendations on the proposed development concept.
(B) Following the meeting, the Chief Subdivision Engineer must provide a written report to the applicant containing the written comments of reviewers along with instructions for proceeding with the subdivision process.
(Ord. passed 7-8-1970; Res. 09-167, passed 6-18-2009)