The Director may issue a permit to a property owner authorizing construction of a temporary on-site wastewater system when the Director determines that it is highly probable that the property will have access to a public sewer within 24 months from the date of a permit application and owner is able to demonstrate the ability to install a permanent on-site wastewater system in accordance with provisions of this chapter. As a condition of the permit, the property owner and the Director shall enter into a written agreement, and the permit and the agreement shall contain the following terms:
(a) The permittee agrees to connect the property to the sanitary sewer within 30 days after it becomes available to the property.
(b) If the public sewer does not become available to the property within the period of time specified in the agreement the property owner shall apply for a permit for an on-site wastewater treatment system within 30 days after receiving notice from the Director and install an approved on-site wastewater treatment system within one year from the date the Director issues the permit.
(c) The property owner will pump and remove all sewage and other wastes from the temporary on-site wastewater system and abandon the system following the procedures in section 68.314.
(d) The property owner will not occupy the building to which the temporary on-site wastewater system will be installed or allow any other person to occupy the building until the property owner installs the system and the Director approves it.
(e) If the property owner sells or transfers the property the permit to use the temporary system will terminate unless the purchaser or transferee enters into a new agreement with the Director.
(Amended by Ord. No. 6049 (N.S.), effective 6-11-81; amended by Ord. No. 7428 (N.S.), effective 2-4-88; amended by Ord. No. 9273 (N.S.), effective 12-15-00; amended by Ord. No. 10136 (N.S.), effective 4-15-11)