(a) If the Director determines that repairing a defective system is infeasible, the Director may require the building owner to connect the building's drainage system to a public sewer, whether or not that sewer is adjacent to the property or accessible without the property owner having to acquire an additional easement.
(b) Where connection to a public sewer does not require annexation to a sewer district or the acquisition of an additional easement, the property owner shall connect the building's drainage system to the public sewer within 90 days after the system became defective. When connection to a public sewer requires annexation or requires acquisition of an additional easement, the property owner shall connect to the public sewer within 180 days after the system became defective. The Director may allow the property owner additional time if the property owner has initiated legal action to acquire the necessary easement and is diligently pursuing the action.
(Added by Ord. No. 9665 (N.S.), effective 8-14-04; amended by Ord. No. 10136 (N.S.), effective 4-15-11)