SECTION:
Article I. Building Permits
18.188.010: Required, When
18.188.020: Application
18.188.030: Issuance Restrictions; Generally
18.188.040: Issuance Restrictions; Prohibited Structures
18.188.050: Issuance Restrictions; Certain Residential Buildings
18.188.060: Dedication Of Streets Required
18.188.070: Improvements Required
18.188.080: Issuance Restrictions; Flood Hazard Areas
Article II. Certificate Of Occupancy And Zoning Clearance
18.188.090: Prerequisites To Building Occupancy
18.188.100: New Buildings
18.188.110: Existing Buildings And Undeveloped Land
ARTICLE I. BUILDING PERMITS
It is unlawful for any property owner, or his authorized agent, to commence any work pertaining to the erection, construction, reconstruction, moving, conversion or alteration of any building, or any addition to any building, until a building permit has first been secured from the director of building and safety for such work. (Ord. 1000 § 33.00(A)(1), 1955)