The following definitions shall apply throughout this article:
(a) “Awarding Authority” means the governing body, board, officer or employee of the City or City Financial Assistance Recipient authorized to award a Contract and shall include a department which has control of its own funds if the department adopts policies consonant with the provisions of this article.
(b) “City” means the City of Los Angeles and all Awarding Authorities thereof.
(c) “City Financial Assistance Recipient” means any person who receives from the City in any 12-month period discrete financial assistance for economic development or job growth expressly articulated and identified by the City totaling at least $100,000; provided, however, that corporations organized under Section 501(c)(3) of the United States Internal Revenue Code of 1954, 26 U.S.C. § 501(c)(3), with annual operating budgets of less than $5,000,000, or that regularly employ homeless persons, persons who are chronically unemployed, or persons receiving public assistance, shall be exempt.
Categories of such assistance include, but are not limited to, bond financing, planning assistance, tax increment financing exclusively by the City, and tax credits, and shall not include assistance provided by the Community Development Bank. City staff assistance shall not be regarded as financial assistance for purposes of this article. A loan at market rate shall not be regarded as financial assistance. The forgiveness of a loan shall be regarded as financial assistance. A loan shall be regarded as financial assistance to the extent of any differential between the amount of the loan and the present value of the payments thereunder, discounted over the life of the loan by the applicable federal rate as used in 26 U.S.C. §§ 1274(d) and 7872(f). A recipient shall not be deemed to include lessees and sublessees. Contracts for economic development or job growth shall be deemed providing such assistance once the $100,000 threshold is reached.
(d) “Contract” means:
(1) a contract let to a Contractor by the City or a City Financial Assistance Recipient primarily for the furnishing of services to or for the City or City Financial Assistance Recipient (as opposed to the purchase of goods or other property) and that involves an expenditure or receipt in excess of $25,000 and a contract term of at least three months; or
(2) a Public Lease or License as those terms are defined in Los Angeles Administrative Code Section 10.37.1(k) but only if the lessee or licensee is subject to the Living Wage Ordinance and not otherwise exempt from its provisions.
(e) “Contractor” means any person that enters into a Contract with the City or a City Financial Assistance Recipient. Governmental entities, including public educational institutions and public hospitals, are not Contractors and are not subject to this article.
(f) “Designated Administrative Agency (DAA)” means the Department of Public Works, Bureau of Contract Administration, which shall bear administrative responsibilities under this article.
(g) “Employee” means any person employed as an employee of a Contractor or Subcontractor earning no more than twice the hourly wage without health benefits available under the Living Wage Ordinance, Los Angeles Administrative Code Section 10.37 et seq., whose primary place of employment is in the City on or under the authority of a Contract. Examples of Employee includes: hotel Employees; restaurant, food service or banquet Employees; janitorial Employees; security guards; parking attendants; nonprofessional health care Employees; gardeners; waste management Employees; and clerical Employees. Employee does not include a person who is a managerial, supervisory or confidential Employee. An Employee must have been employed by a terminated Contractor for the preceding 12 months or longer.
(h) “Person” means any individual, proprietorship, partnership, joint venture, corporation, limited liability company, trust, association or other entity that may employ individuals or enter into contracts.
(i) “Subcontractor” means any person not an Employee who enters into a contract with a Contractor to assist the Contractor in performing a Contract and who employs Employees for such purpose. A Subcontractor includes a sublessee or sublicensee.
(j) “Successor Contract” means a Contract where the service to be performed is substantially similar to the Contract recently terminated. The meaning also includes a Contract that is a Public Lease or License substantially similar to a Public Lease or License recently terminated. Termination includes, but is not limited to: (1) the completion of the Contract; (2) early termination of the Contract in whole or in part; or (3) an amendment that reduces services provided under the Contract, in whole or in part.
SECTION HISTORY
Added by Ord. No. 170,784, Eff. 1-13-96.
Amended by: Ord. No. 171,004, Eff. 5-18-96; Subsec. (c), Ord. No. 172,843, Eff. 11-4-99; Subsec. (j) added, Ord. No. 176,155, Eff. 9-22-04; Subsec. (j), Ord. No. 176,283, Eff. 12-25-04, Oper. 9-22-04; In Entirety, Ord. No. 184,293, Eff. 6-27-16; In Entirety, Ord. No. 185,356, Eff. 1-26-18.
(a) Within ten days of learning that a Contract is to be terminated, the Contractor shall provide to the Successor Contractor, the Awarding Authority and the DAA, the name, address, date of hire, and employment occupation classification of each Employee of the terminated Contractor and Subcontractor working pursuant to the Contract. If the terminated Contractor has not learned the identity of the Successor Contractor, the Contractor shall request the identity from the Awarding Authority. If a Successor Contract has not been awarded by the end of the ten-day period, the Contractor shall provide the employment information referred to earlier in this subsection to the Awarding Authority and the DAA. Where only a subcontract of a Contract has been terminated, the terminated Subcontractor shall for purposes of this Article be deemed a terminated Contractor.
(1) If multiple Contracts providing similar services are terminated, the Awarding Authority shall consult with the DAA to determine whether to pool the Employees, ordered by seniority within job classification and provide a pool list to the Successor Contractor. The Successor Contractor shall provide written notice to the Awarding Authority and the DAA that the Awarding Authority’s pool list will be used. The notice must include the following:
(A) the total number of Employees required under the Successor Contract;
(B) a breakdown of the number of Employees required within each job classification and seniority within each class; and
(C) an indication as to which Employees within each job classification shall be offered employment under this article.
The written notice must be provided no later than ten days after the Successor Contractor receives the listing of the terminated Contractor’s Employees.
(2) Where the use of Subcontractors has occurred under the terminated Contract or where the use of Subcontractors is to be permitted under the Successor Contract, or where both circumstances arise, the Awarding Authority shall pool, when applicable, the Employees, ordered by seniority within job classification, under such prior Contracts or subcontracts where required by, and in accordance with, rules promulgated by the DAA. The Successor Contractor or Subcontractor shall provide written notice to the Awarding Authority and the DAA that the Awarding Authority’s pool list will be used.
(b) If work-related requirements for a particular job classification under the Successor Contract differ from the terminated Contract, the Successor Contractor (or Subcontractor, where applicable) shall give notice to the Awarding Authority and the DAA and provide an explanation including:
(1) the different work-related requirements needed; and
(2) the reason why the different work-related requirements are necessary for the Successor Contract.
(c) Within ten days of receipt of the list of Employees from the terminated Contractor, the Successor Contractor shall make written offers for a 90-day transition employment period to the eligible Employees by letters sent certified mail. The letters shall ask an Employee to return the offers to the Successor Contractor with the Employee’s signature indicating acceptance or rejection of the offer of employment. The letters shall state that if an Employee fails to return a written acceptance of the offer within ten days of the date of mailing of the Successor Contractor’s certified letter, then the Employee will be presumed to have declined the offer.
The Successor Contractor shall provide copies of the letters offering employment to the Awarding Authority and proof of mailing.
(d) A Successor Contractor shall retain Employees for a 90-day transition employment period. Where pooling of Employees has occurred, the Successor Contractor shall draw from the pools in accordance with rules promulgated by the DAA. During such 90-day period, Employees so hired shall be employed under the terms and conditions established by the Successor Contractor (or Subcontractor) or as required by law.
(e) If at any time the Successor Contractor determines that fewer Employees are required to perform the new Contract than were required by the terminated Contractor (and Subcontractors, if any), the Successor Contractor shall retain Employees by seniority within job classification. The Successor Contractor shall give notice to the Awarding Authority and the DAA and provide an explanation including:
(1) the reason that fewer Employees will be needed;
(2) the total number of Employees required under the Successor Contract;
(3) a breakdown of the number of Employees required within each job classification;
(4) a listing of the terminated Contractor’s Employees by job classification and seniority within each class; and
(5) an indication as to which Employees within each job classification will be offered employment under this article.
The notice must be provided no later than ten days after the Successor Contractor receives the list of the terminated Contractor's Employees pursuant to Section 10.36.2(a).
Letters offering employment shall be made by seniority within each job classification. If an Employee in a job classification declines an offer of employment or fails to respond within ten days pursuant to Section 10.36.2(a), the Successor Contractor shall issue a letter offering employment to the next Employee in that job classification. The Successor Contractor shall continue to offer employment in this manner until all required positions are filled for the Successor Contract or until all Employees have been offered employment.
(f) During the 90-day transition employment period, the Successor Contractor (or Subcontractor, where applicable) shall maintain a preferential hiring list of eligible covered Employees not retained by the Successor Contractor (or Subcontractor) from which the successor Contractor (or Subcontractor) shall hire additional Employees, if needed.
(g) During the 90-day transition employment period, the Successor Contractor (or Subcontractor, where applicable) shall not discharge without cause an Employee retained pursuant to this article. “Cause” for this purpose shall mean fair and honest reasons, regulated by good faith on the part of the Contractor or Subcontractor, that are not trivial, arbitrary or capricious, unrelated to business needs or goals, or pretextual.
(h) At the end of the 90-day transition employment period, the Successor Contractor (or Subcontractor, where applicable) shall perform a written performance evaluation for each Employee retained pursuant to this article. If the Employee’s performance during the 90-day period is satisfactory, the Successor Contractor (or Subcontractor) shall offer the Employee continued employment under terms and conditions established by the Successor Contractor (or Subcontractor) or as required by law.
(i) If the City or a City Financial Assistance Recipient enters into a Contract for the performance of work that prior to the Contract was performed by the City’s or the City Financial Assistance Recipient’s own Employees, the City or the City Financial Assistance Recipient shall be deemed to be a terminated Contractor within the meaning of this article and the Contractor shall be deemed to be a Contractor with a Successor Contract within the meaning of this article.
SECTION HISTORY
Added by Ord. No. 170,784, Eff. 1-13-96.
Amended by: Ord. No. 171,004, Eff. 5-18-96; Subsec. (g) Added, Ord. No. 172,349, Eff. 1-29-99; In Entirety, Ord. No. 184,293, Eff. 6-27-16; In Entirety, Ord. No. 185,356, Eff. 1-26-18.
(a) An Employee who has been discharged in violation of this article by a Successor Contractor or its Subcontractor may bring an action in the Superior Court of the State of California against the Successor Contractor and, where applicable, its Subcontractor, and may be awarded:
(1) Back pay for each day during which the violation continues, which shall be calculated at a rate of compensation not less than the higher of:
(A) The average regular rate of pay received by the Employee from the terminated Contractor during the last three years of the Employee’s employment in the same occupation classification; or
(B) The final regular rate paid by the terminated Contractor to the Employee.
(2) Costs of benefits the Successor Contractor would have incurred for the Employee under the successor Contractor’s (or Subcontractor’s, where applicable) benefit plan.
(b) If the Employee is the prevailing party in any such legal action, the court shall award reasonable attorney’s fees and costs as part of the costs recoverable.
(c) Compliance with this article shall be required in all Contracts and shall provide that violation of this article shall entitle the City to terminate the Contract and pursue all legal remedies.
(d) If the DAA determines that a Contractor or Subcontractor violated this article, the DAA may recommend that the Awarding Authority take any or all of the following actions:
(1) Document the determination in the Awarding Authority’s Contractor Evaluation required under Los Angeles Administrative Code Section 10.39, et seq.;
(2) Require that the Contractor or Subcontractor document the determination in each of the Contractor’s or Subcontractor’s subsequent Contractor Responsibility Questionnaires submitted under Los Angeles Administrative Section 10.40, et seq.;
(3) Terminate the Contract;
(4) Recommend to the Awarding Authority to withhold payments due to the Contractor or Subcontractor.
(e) Notwithstanding any provision of this Code or any other law to the contrary, no criminal penalties shall attach for any violation of this article.
SECTION HISTORY
Added by Ord. No. 170,784, Eff. 1-13-96.
Amended by: Ord. No. 171,004, Eff. 5-18-96; In Entirety, Ord. No. 184,293, Eff. 6-27-16; In Entirety, Ord. No. 185,356, Eff. 1-26-18.
(a) An Awarding Authority may allow a Successor Contractor or Subcontractor to fill a position under a Contractor with a person who has been employed by the Contractor or Subcontractor continuously for at least 12 months prior to the commencement of the Successor Contract working in a position similar to the position to be filled in the Successor Contract. The Successor Contractor or Subcontractor shall first obtain written approval of the Awarding Authority by demonstrating that: (a) the person would otherwise be laid off work; and (b) the person’s retention would be helpful to the Contractor or Subcontractor in performing the Successor Contract.
(b) Nothing in this article shall limit the right of the DAA to waive the provisions herein with respect to a Contractor if it finds it is not in the best interest of the City.
SECTION HISTORY
Added by Ord. No. 170,784, Eff. 1-13-96.
Amended by: Ord. No. 171,004, Eff. 5-18-96; In Entirety, Ord. No. 184,293, Eff. 6-27-16; In Entirety, Ord. No. 185,356, Eff. 1-26-18.
This article shall not be construed to limit an Employee's right to bring legal action for wrongful termination.
SECTION HISTORY
Added by Ord. No. 170,784, Eff. 1-13-96.
Amended by: Ord. No. 171,004, Eff. 5-18-96; In Entirety, Ord. No. 184,293, Eff. 6-27-16; In Entirety, Ord. No. 185,356, Eff. 1-26-18.
This article shall apply to the expenditure, whether through Contracts let by the City or by City Financial Assistance Recipients, of funds entirely within the City’s control and to other funds, such as federal or state grant funds, where the application of this article is consonant with the laws authorizing the City to expend such other funds. City Financial Assistance Recipients shall apply this article to the expenditure of non-City funds for Contracts to be performed in the City by complying with Section 10.36.2(i) and by contractually requiring their Contractors with Contracts to comply with this article. Such requirement shall be imposed by the recipient until the City financial assistance has been fully expended.
SECTION HISTORY
Added by Ord. No. 171,004, Eff. 5-18-96.
Amended by: Ord. No. 172,337, Eff. 1-14-99; Ord. No. 172,843, Eff. 11-4-99; In Entirety, Ord. No. 184,293, Eff. 6-27-16; In Entirety, Ord. No. 185,356, Eff. 1-26-18.
The DAA shall promulgate rules for implementation of this article and otherwise coordinate administration of the requirements of this article.
SECTION HISTORY
Added by Ord. No. 171,004, Eff. 5-18-96.
Amended by: Ord. No. 176,155, Eff. 9-22-04; Ord. No. 176,283, Eff. 12-25-04, Oper. 9-22-04; In Entirety, Ord. No. 184,293, Eff. 6-27-16; In Entirety, Ord. No. 185,356, Eff. 1-26-18.
If any subsection, sentence, clause or phrase of this article is for any reason held to be invalid or unconstitutional by a court of competent jurisdiction, such decision shall not affect the validity of the remaining portions of this ordinance. The City Council hereby declares that it would have adopted this section, and each and every subsection, sentence, clause and phrase thereof not declared invalid or unconstitutional, without regard to whether any portion of the ordinance would be subsequently declared invalid or unconstitutional.
SECTION HISTORY
Added by Ord. No. 171,004, Eff. 5-18-96.
Amended by: In Entirety, Ord. No. 184,293, Eff. 6-27-16; In Entirety, Ord. No. 185,356, Eff. 1-26-18.