“Commenced” means an owner or operator has undertaken a continuous program of construction, installation or modification or has entered into a binding contractual obligation to undertake and complete, within a reasonable time, a continuous program of construction, installation or modification.
(Ord. No. 857-A-76. Passed 6-27-77, eff. 6-30-77)
“Compliance schedule” means a plan of corrective action to achieve full compliance with the provisions of this Code, submitted as part of a variance application. This schedule may include the following milestones, each to be achieved at the earliest possible date:
(a) Submission of final control plans for source;
(b) Awarding of contracts for emission control systems or issuing of purchase orders for component parts to accomplish emission control or process modification;
(c) Initiation of on-site construction or installation of emission control equipment or process modification;
(d) Completion of on-site construction or installation of emission control equipment or process modification;
(e) Achievement of final compliance with all provisions of the Air Pollution Code of the City of Cleveland.
(Ord. No. 857-A-76. Passed 6-27-77, eff. 6-30-77)
“Effluent water separator” means any tank, box, sump or other container in which any volatile photochemically reactive material floating on or entrained or contained in water entering such tank, box, sump or other container is physically separated and removed from such water prior to outfall, drainage or recovery of such water.