The developer, their successors or assigns, if any, shall construct, at their cost, all sanitary sewer service for service to the Jordan Heights development as required by city of West Des Moines subdivision ordinance and the Des Moines metro standards with West Des Moines addendums.
The developer, their successors or assigns, if any, shall construct, at their cost, all water mains for water service to the Jordan Heights development as required by West Des Moines waterworks during the time the site plan is being developed. This requirement includes water mains in the specific plan and in street right of way adjacent to the specific plan area. The sizes of all water mains shall be determined by the waterworks. Water mains shall be constructed along the entire street frontages of the specific plan.
Nothing in this ordinance shall be construed to prevent the developer, their successors or assigns, if any, from entering into private agreement(s) as they may desire to share the cost of the water mains. (Ord. 1854, 1-11-2010)