Completed construction documents complying with the provisions of this code and other applicable laws and rules shall be approved by the commissioner and written notice of approval shall be given the applicant promptly and no later than 40 calendar days after the submission of a complete application.
Exceptions:
1. On or before the fortieth day, the commissioner may, for good cause shown and upon notification to the applicant, extend such time for an additional 20 calendar days.
2. Such time period for review shall commence in accordance with article 107 for single room occupancy multiple dwellings.
The department shall, on a weekly basis, send council members and community boards, by electronic mail, and post on its website, a report of all applications that were approved during the prior week, disaggregated by community board, for:
1. A new building or an alteration that will require a new certificate of occupancy for a building; and
2. Work at a building or part thereof for which construction and related documents shall not be accepted with less than full examination by the department pursuant to the exception to section 28-104.2.1.
(L.L. 2016/010, 2/8/2016, eff. 5/8/2016; Am. L.L. 2017/158, 8/30/2017, eff. 8/30/2018; Am. L.L. 2021/126, 11/7/2021, eff. 11/7/2022)
Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.
Applications failing to comply with the provisions of this code and other applicable laws and rules shall be rejected and written notice of rejection, stating the grounds of rejection, shall be given the applicant promptly and not later than the date required in section 28-104.2.7. The department shall, on a weekly basis, send council members and community boards, by electronic mail, a report of all rejections of applications for a new building or an alteration that will require a new certificate of occupancy for a building, during the prior week, disaggregated by community board. In addition, the department shall post such information on its website on a weekly basis.
(Am. L.L. 2016/010, 2/8/2016, eff. 5/8/2016; Am. L.L. 2021/126, 11/7/2021, eff. 11/7/2022)
Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.
Whenever an application has been rejected and is thereafter revised and resubmitted to meet the stated grounds of rejection, the revised application and construction documents shall be approved if they meet the stated grounds of rejection and otherwise comply with the provisions of this code and other applicable laws and rules or shall be rejected if they fail to meet the stated grounds of rejection or otherwise fail to so comply.
The commissioner may, on notice to the applicant, revoke the approval of construction documents for failure to comply with the provisions of this code or other applicable laws or rules; or whenever there has been any false statement or any misrepresentation as to a material fact in the submittal documents upon the basis of which such approval was issued; or whenever an approval has been issued in error and conditions are such that approval should not have been issued. Such notice shall inform the applicant of the reasons for the proposed revocation and that the applicant has the right to present to the commissioner or his or her representative within 10 business days of personal service or electronic delivery or 15 business days of the posting of service by mail, information as to why the approval should not be revoked.
(Am. L.L. 2021/126, 11/7/2021, eff. 11/7/2022)
Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.
Subject to the time limitations set forth in this code, amendments to approved construction documents shall be submitted, reviewed and approved before the work or equipment is completed; and such amendments when approved shall be deemed part of the original construction documents. The department may allow minor revisions of construction documents to be made and submitted to the department after the completion of work but prior to sign-off of the work. All other revisions of construction documents shall be submitted and approved prior to commencing the work effectuating such revisions.
(Am. L.L. 2021/126, 11/7/2021, eff. 11/7/2022)
Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.