§ 54.09 LARGE POWER RATE (SCHEDULE LP).
   (A)   Applicable:
      (1)   This rate is available, upon application, to power consumers for power, including lighting, where the monthly maximum demand of the consumer is at least 500 kilowatts each and every month of the past 12 (immediate preceding) billing months.
      (2)   This rate is not available for auxiliary, standby, or supplementary service.
   (B)   Character of service: Any secondary or primary voltage designated by the village. All services are to be three phase, 60 hertz, with balanced three phase loading. All energy shall be secondary metered unless the village desires primary metering in which case the kilowatt-hours and kilowatt and kilovar demands shall be adjusted to reflect consumption as subsequently stated herein.
   (C)   Monthly customer charge per meter per month: $50.00.
   (D)   Demand charge:
      (1)   First 500 kW or less of billing demand per month: $7,500.
      (2)   Over 500 kW of billing demand per month, per kilowatt: $15.00.
   (E)   Energy charges:
      For each kilowatt-hour of billing energy per month: $0.060.
   (F)   Reactive charge:
      All kilovar of reactive billing demand per month: $0.75.
   (G)   Excise (kilowatt-hour) tax adjustment: For all customers located outside the village's corporation limits, the rates set forth above shall be increased by an amount equal to excise (kilowatt-hour) tax imposed on the village's electrical distribution system under R.C. § 5727.81. Said increase shall become effective with the bills that include May 1, 2001 as part of the usage period and shall be automatically adjusted to reflect any change in the kilowatt-hour tax imposed by R.C. § 5727.81.
   (H)   Power cost adjustment: The above rates shall be adjusted in accordance with the power cost adjustment set forth in § 54.07.
   (I)   Delayed payment charge: Ten percent shall be added to the net bill if not paid full within 15 days after rendition of bill for said service.
   (J)   Determination of billing demand: The billing demand shall be in 15-minute integrated demand, ascertained in kilowatts by instruments suitable for that purpose. Billing shall be on a monthly basis and the monthly billing demand shall be the greater of the following:
      (1)   Off-peak: Seventy percent of the greatest such demand occurring during the billing month, either within the period between 11:00 p.m. of one day and 7:00 a.m. the following day or on a Saturday or Sunday, or on New Years Day, Memorial Day, Independence Day, Labor Day Thanksgiving Day or Christmas Day; or
      (2)   On-peak: One hundred percent of the greatest such demand occurring during the billing month at any time not within the period and not on the days specifically mentioned in division (J)(1) above.
   (K)   On-site generation: On-site generating capacity will be limited to customer's estimated peak load. Where on-site generation is installed, the monthly billing demand will be equal to the billing demand that would have been billed absent the on-site generation.
   (L)   Meter voltage adjustment: These rates are based on service metered at secondary voltage. When at the option of the village service is metered at a primary voltage the metered kilowatt-hours and metered kilowatt and kilovar demands shall be decreased by 1.5% to obtain the billing kilowatt-hours and billing kilowatt and kilovar demands.
   (M)   Service voltage adjustment: When service is provided at primary voltage consumer shall receive a credit of $0.50 per kilowatt of billing demand.
   (N)   Multiple metering points: When service to a single, contiguous facility is metered through multiple metering points, meter data shall be aggregated and treated as one coincident load for billing purposes and determination of the billing kilowatt and kilovar demands.
   (O)   Contract requirements: At the option of the village, service under this rate schedule may only be available under a service contract with consideration for size, character and location of the consumer's load and the amount of facilities to be furnished by the village in serving said load. Contract term initially shall be at least five years.
   (P)   Terms and conditions:
      (1)   All electric service of the village is rendered under and subject to the general service rules and regulations of the village as amended from time to time.
      (2)   This rate is only available upon application in writing to the village and with reasonable lead time for implementation.
(Ord. 15-03-01, passed 4-21-15; Am. Ord. 15-06-01, passed 6-16-15; Am. Ord. 21-03-01, passed 4-6-21)