After the issuance of a permit by the Floodplain Administrator, no changes of any kind shall be made to the application, permit or any of the plans, specifications or other documents submitted with the application without the written consent or approval of the Floodplain Administrator. Requests for any such change shall be in writing, and shall be submitted by the applicant to Floodplain Administrator for consideration.
(Ord. 2015-07, 11/23/2015)
In addition to the permit, the Floodplain Administrator shall issue a placard, or similar document, which shall be displayed on the premises during the time construction is in progress. This placard shall show the number of the permit, the date of its issuance, and be signed by the Floodplain Administrator.
(Ord. 2015-07, 11/23/2015)
1. Work on the proposed construction or development shall begin within 180 days after the date of issuance of the development permit. Work shall also be completed within 12 months after the date of issuance of the permit or the permit shall expire unless a time extension is granted, in writing, by the Floodplain Administrator. The issuance of development permit does not refer to the zoning approval.
2. The actual start of construction means either the first placement of permanent construction of a structure on a site, such as the pouring of slab or footings, the installation of piles, the construction of columns, or any work beyond the stage of excavation; or the placement of a manufactured home on a foundation. Permanent construction does not include land preparation, such as clearing, grading, and filling; nor does it include the installation of streets and/or walkways; nor does it include excavation for a basement, footings, piers, or foundations or the erection of temporary forms; nor does it include the installation on the property of accessory buildings, such as garages or sheds not occupied as dwelling units or not part of the main structure. For a substantial improvement, the actual start of construction means the first alteration of any wall, ceiling, floor, or other structural part of a building, whether or not that alteration affects the external dimensions of the building.
3. Time extensions shall be granted only if a written request is submitted by the applicant, who sets forth sufficient and reasonable cause for the Floodplain Administrator to approve such a request and the original permit is compliant with the Part and FIRM/FIS in effect at the time the extension is granted.
(Ord. 2015-07, 11/23/2015)
1. Notices.
A. Whenever the Floodplain Administrator or other authorized municipal representative determines that there are reasonable grounds to believe that there has been a violation of any provisions of this Part, or of any regulations adopted pursuant thereto, the Floodplain Administrator shall give notice of such alleged violation as hereinafter provided. Such notice shall:
(1) Be in writing;
(2) Include a statement of the reasons for its issuance;
(3) Allow a reasonable time not to exceed a period of 30 days for the performance of any act it requires;
(4) Be served upon the property owner or his agent as the case may require; provided, however, that such notice or order shall be deemed to have been properly served upon such owner or agent when a copy thereof has been served with such notice by any other method authorized or required by the laws of this State;
(5) Contain an outline of remedial actions which, if taken, will effect compliance with the provisions of this Part.
B. Hearings. Any person affected by any notice which has been issued in connection with the enforcement of any provision of this Part, or of any regulation adopted pursuant thereto, may request and shall be granted a hearing on the matter pursuant to §909.1 of the Municipalities Planning Code, 53 P.S. §10909.1.
2. Penalties. Any person who fails to comply with any or all of the requirements or provisions of this Part or who fails or refuses to comply with any notice, order of direction of the Floodplain Administrator or any other authorized employee of the Township for a violation of any provision of this Part, enforcement shall be brought before a magisterial district judge in the same manner provided for the enforcement of summary offenses, or to a term of imprisonment for the failure to pay a fine pursuant to the Pennsylvania Rules of Criminal Procedure. Upon conviction thereof, a violator shall be subject to a criminal fine not to exceed $1000 per violation plus costs, to a term of imprisonment to the extent allowed by law of the punishment of summary offenses, or to a term of imprisonment for the failure to pay a fine pursuant to the Pennsylvania Rules of Criminal Procedures. A separate offense shall arise for each day or portion thereof in which a violation is found to exist or for each section of this Part or other ordinance which is found to have been violated. In addition to the above penalties all other actions are hereby reserved including an action in equity for the proper enforcement of this Part. The imposition of a fine or penalty for any violation of, or noncompliance with this Part shall not excuse the violation or noncompliance or permit it to continue. All such persons shall be required to correct or remedy such violations and noncompliance within a reasonable time. Any development initiated or any structure or building constructed, reconstructed, enlarged, altered, or relocated, in noncompliance with this Part may be declared by the Board of Supervisors to be a public nuisance and abatable as such.
(Ord. 2015-07, 11/23/2015)
1. Any person aggrieved by any action or decision of the Floodplain Administrator concerning the administration of the provisions of this Part, may appeal to the Zoning Hearing Board. Such appeal must be filed, in writing, within 30 days after the decision, determination, or action of the Floodplain Administrator.
2. Upon receipt of such appeal the Zoning Hearing Board shall consider the appeal in accordance with the Municipal Planning Code and any other local Part.
3. Any person aggrieved by any decision of the Zoning Hearing Board may seek relief therefrom by appeal to court, as provided by the laws of this state including the Pennsylvania Flood Plain Management Act.
(Ord. 2015-07, 11/23/2015)
C. Identification of Floodplain Areas
1. The identified floodplain area shall be:
A. Any areas of Township of Dover, classified as Special Flood Hazard Areas (SFHAs) in the Flood Insurance Study (FIS) and the accompanying Flood Insurance Rate Maps (FIRMs) dated December 16, 2015 and issued by the Federal Emergency Management Agency (FEMA) or the most recent revision thereof, including all digital data developed as part of the flood insurance.
2. The above referenced FIS and FIRMs, and any subsequent revisions and amendments are hereby adopted by Township of Dover and declared to be a part of this Part.
(Ord. 2015-07, 11/23/2015)
The identified floodplain area shall consist of the following specific areas:
A. The floodway area shall be those areas identified in the FIS and the FIRM as floodway and which represent the channel of a watercourse and the adjacent land areas that must be reserved in order to discharge the base flood without increasing the water surface elevation by more than one foot at any point. This term shall also include floodway areas which have been identified in other available studies or sources of information for those special flood hazard areas where no floodway has been identified in the FIS and FIRM.
(1) Within any floodway area, no encroachments, including fill, new construction, substantial improvements, or other development shall be permitted unless it has been demonstrated through hydrologic and hydraulic analysis performed in accordance with standard engineering practice that the proposed encroachment would not result in any increase in flood levels within the community during the occurrence of the base flood discharge.
(2) Within any floodway area, no new construction or development shall be allowed, unless the appropriate permit is obtained from the Department of Environmental Protection Regional Office.
B. The AE Area/District shall be those areas identified as an AE Zone on the FIRM included in the FIS prepared by FEMA for which base flood elevations have been provided.
(1) The AE Area adjacent to the floodway shall be those areas identified as an AE Zone on the FIRM included in the FIS prepared by FEMA for which base flood elevations have been provided and a floodway has been delineated.
C. The A Area/District shall be those areas identified as an A Zone on the FIRM included in the FIS prepared by FEMA and for which no base flood elevations have been provided. For these areas, elevation and floodway information from other federal, state, or other acceptable sources shall be used when available. Where other acceptable information is not available, the base flood elevation shall be determined by using the elevation of a point on the boundary of the identified floodplain area which is nearest the construction site.
(1) In lieu of the above, the Township may require the applicant to determine the elevation with hydrologic and hydraulic engineering techniques. Hydrologic and hydraulic analyses shall be undertaken only by professional engineers or others of demonstrated qualifications, who shall certify that the technical methods used correctly reflect currently accepted technical concepts. Studies, analyses, computations, etc., shall be submitted in sufficient detail to allow a thorough technical review by the Township.
D. The AO and AH Area/ District shall be those areas identified as Zones AO and AH on the FIRM and in the FIS. These areas are subject to inundation by 1-percent-annual-chance shallow flooding where average depths are between one and three feet. In Zones AO and AH, drainage paths shall be established to guide floodwaters around and away from structures on slopes.
(Ord. 2015-07, 11/23/2015)
The identified floodplain area may be revised or modified by the Board of Supervisors where studies or information provided by a qualified agency or person documents the need for such revision. However, prior to any such change to the special flood hazard area, approval must be obtained from FEMA. Additionally, as soon as practicable, but not later than six months after the date such information becomes available, a community shall notify FEMA of the changes to the special flood hazard area by submitting technical or scientific data. See § 4-141B. for situations where FEMA notification is required.
(Ord. 2015-07, 11/23/2015)