(A) The owner of each building within the scope of this chapter shall cause a structural analysis of the building to be made by a civil or structural engineer or architect licensed by the State of California. If the building does not meet the minimum earthquake standards specified in this chapter, the owner shall either cause it to be structurally altered to conform to such standards or cause the building to be demolished.
(B) The owner of a building within the scope of this chapter shall comply with the requirements set forth above by submitting to the Building Official for review within the stated time limits:
(1) Within 270 days after the service of the order, a structural analysis which is subject to approval by the Building Official and which shall demonstrate that the building meets the minimum requirements of this chapter;
(2) Within 270 days after the service of the order, the structural analysis and plans for the proposed structural alterations of the building necessary to comply with the minimum requirements of this chapter;
(3) Within 120 days after service of the order, plans for the installation of wall anchors in accordance with the requirements specified in § 15.64.080; or
(4) Within 270 days after the service of the order, plans for the demolition of the building.
(C) After plans are submitted and approved by the Building Official, the owner shall obtain a building permit, commence and complete the required construction or demolition within the time limits set forth in Table B. These time limits shall begin to run from the date the order is served in accordance with § 15.64.070 (A) and (B). Owners electing to comply with subsection (B)(3) of this section are also required to comply with subsections (B)(2) and (B)(4) of this section; provided, however, that the 270 day period provided for in such subsections (B)(2) and (4) and the time limits for obtaining a building permit, commencing construction and completing construction for complete structural alterations or building demolition set forth in Table B shall be extended in accordance with Table C. Each such extended time limit, except the time limit for commencing construction, shall begin to run from the date the order is served in accordance with § 15.64.070(B). The time limit for commencing construction shall commence from the date the building permit is issued.
(`78 Code, § 15.64.060.) (Ord. 1967 § 1 (part), 1989.)