13.20.120 Construction, service connection – City action.
   The notice given by the City Engineer to provide the required underground facilities shall particularly specify what work is required to be done and shall state that if the work is not completed within 30 days after receipt of the notice, the City Engineer will provide such required underground facilities, in which case the cost and expense thereof will be assessed against the property benefitted and become a lien upon the property.
(`78 Code, § 13.20.120.)