13.20.100 Construction, service connection – Property owner responsibility designated.
   Every person owning, operating, leasing, occupying or renting a building or structure within a district shall construct and provide that portion of the service connection on his or her property between the facilities referred to in § 13.20.090 and the termination facility on or within the building or structure being served. If this required construction is not accomplished by any person within the time provided for in the resolution enacted pursuant to § 13.20.040, the City Engineer shall give notice in writing to the person in possession of such premises and a notice in writing to the owner thereof as shown on the last equalized assessment roll to provide the required underground facilities within ten days after the receipt of the notice.
(`78 Code, § 13.20.100.)