§ 523.23 Pole and Anchor Attachments
   The following schedule is applicable to any attachment of communication facilities to poles owned by the Division of Cleveland Public Power ("attachments") by any person or entity ("permittee") other than a joint owner of such pole or a party to any joint use agreement.
   (a)   Application for Attachment. Any person or entity desiring to install attachments shall make a written request for permission to install attachments on any pole owned by the Division of Cleveland Public Power. The request shall specify the location of each pole, the identifying number of each pole, the nature of the proposed attachment and the amount and location of space desired. Within thirty (30) days after receipt of a written request, the Division shall notify the applicant whether or not it will permit the attachment and under what conditions. The Division shall have the sole right to determine whether an attachment would adversely affect its electric utility services and its ability to provide such services in an economic and safe manner, including considerations for the future needs of its customers.
   (b)   Conditions of Attachment. All attachments shall be placed on Division's poles in a manner satisfactory to the Division and shall not interfere with the present or future use of the pole by the Division. All attachments shall be installed and at all times maintained by the permittee so as to comply with the requirements of the National Electrical Safety Code and other applicable Federal, State, County, or Municipal codes, as well as operating procedures of the Division of Cleveland Public Power. The permittee shall be responsible for obtaining any right, license or permit from any governmental body, authority, or other person or persons which may be required for the construction and maintenance of the attachments of the permittee, including easements, rights-of-way, or rights of entry upon premises.
   If the Division desires to replace an existing pole, or add facilities to an existing pole, to which the permittee has made attachments, the permittee shall, where required by the Division, relocate its facilities at its own expense.
   In the event that a permittee fails to make or maintain any attachments in conformance to all applicable codes and procedures, the Division, after fifteen (15) days’ written notice, shall have the right to make, or cause to be made, the necessary corrections or shall have the right to remove such attachments, without liability, at the entire expense of the permittee.
   In the event of any emergency which, in the opinion of the Division, affects or threatens to affect the operations of the Division, the Division shall have the right to perform such detachment, disconnection, relocation or alteration, at the permittee’s expense, of such attachments as may be necessary to meet such emergency.
   (c)   Attachment Rental Fee.
   $0.25 per month for each pole attachment
   $0.50 per month for each anchor attachment
   Attachment rental fees shall be billed monthly and shall be due and payable on or before twenty-one (21) calendar days following the date on which the bill is issued. Payments received after the due date shall be subject to the same penalty as prescribed in Section 523.12. The bill for attachment rental fees will reflect the total number of attachments in place during the previous month.
   Within five (5) days following the end of each calendar month, the permittee shall notify the Division, in writing, of the completion of all attachments, or removal thereof, during the preceding month.
   (d)   Reimbursement of Costs. If attachment to the Division’s poles imposes on the Division costs which would not otherwise be incurred, the party requesting attachment shall reimburse the Division for all such costs. Such costs may include, but are not necessarily limited to any change in or strengthening of poles, any rearrangement, alteration or addition, or other changes in existing facilities, which in the opinion of the Division are necessary to accommodate the attachments of the party or entity requesting an attachment. Such costs may also include billing, engineering, and any necessary evaluation of the applicant’s request for attachments. The Division reserves the right to require the permittee to have all necessary work performed at the permittee’s expense by a contractor engaged by the permittee and approved by the Division, performing work in construction standards of the Division.
   (e)   Multiple Applicants for Attachment. When the Division receives application from more than one (1) applicant for permission to attach to any pole and, because of such multiple attachments, either the pole must be replaced or the facilities thereon must be rearranged to provide additional space for the attachments, the Division may apportion the additional total costs resulting from the pole replacement or rearrangement among all permittees. Such apportioned costs shall include common engineering, material and other expenses which result from the multiple applications and the multiple attachments. The permittee shall be bound by the Division’s determination as to any such apportionment of costs.
   (f)   Power Supplies and Amplifiers. Power supplies and amplifiers may be mounted on the Division’s poles at the sole discretion of the Division. Permittee shall request permission to mount such facilities in writing to the Division. The location and design shall be approved by the Division prior to installation.
   Any electric service for power supplies and amplifiers shall be paid for by the permittee at the Division’s applicable electric rate. The meter, if required, will be furnished by the Division. The meter base will be furnished by the Division and installed by the permittee according to standards set forth by the Division. The permittee’s service conductors, if required, shall be furnished and installed by the permittee with weatherhead included. Sufficient conductor shall be left to reach the Division’s secondary circuit. The permittee shall ensure that all equipment is effectively grounded to an earth ground, separate and apart from any ground wire belonging to the Division, and shall observe the National Electrical Safety Code and all other applicable codes in the installation of these facilities.
   Power supplies and amplifiers will not be permitted on poles which have transformers, reclosers, cut-outs, oil switches, capacitors, or other equipment of a size or type which would impair climbing or working space if an additional pole-mounted facility were installed. Power supplies and amplifiers may be prohibited in situations deemed sensitive from the standpoint of pole line appearance. The permittee shall install all of its attachments so as to not interfere with climbing space as defined by the National Electrical Safety Code or specifically defined by the Division.
   (g)   Inspection of Facilities. The Division shall have the right to inspect each installation of the permittee upon its poles and thereafter to make periodic inspections. The permittee shall reimburse the Division for the expense of such inspection, which reimbursement for any pole subject hereto, shall not exceed in any year the expense of one (1) inspection.
   The right to make such inspections and any inspection made shall not impose any obligation or liability on the Division nor shall it relieve the permittee of any responsibility, obligation, or liability.
   (h)   Indemnification. The permittee shall indemnify, hold harmless, and defend the Division from and against any and all actions or causes of actions, claims, demands, liabilities, loss, damage, or expense whatsoever, including attorney’s fees, which the Division may suffer or incur by reason of the failure of the permittee to secure any right, license, permit, or easement required for the construction or maintenance of permittee’s attachments to the Division’s poles, by reason of interruption of permittee’s service to permittee’s subscribers, by reason of bodily injury, including death, to any person or persons, or by reason of damage to or destruction of any property, including the loss of use thereof, arising out of or in any manner connected with the facilities of the permittee to be installed hereunder, or the installation, maintenance, removal, rearrangement or alteration of such facilities by the Division or permittee, or which the Division may sustain or incur in connection with any litigation, investigation, or other expenditures incident thereto including any suit instituted to enforce contractual obligations whether or not due in whole or part to any act, omission, or negligence of the Division, or any of its representatives or employees.
   (i)   Right of Termination. If the permittee fails to comply with any of the provisions of this section or defaults in the performance of any of its obligations under this section and fails to correct such default or non-compliance, the Division may, at its option, remove the permittee’s facilities from the Division’s poles and no liability shall be incurred by the Division because of such action. The permittee shall be liable for the entire cost of removing its attachments from the Division’s poles.
   (j)   Unauthorized Attachments. If equipment or facilities are attached to the Division’s poles for which no attachment is authorized, the Division may require the owner of the attached facilities to remove the attachments immediately at the owner’s cost, or the Division may remove the facilities at the expense of the owner of the attachments without liability to the Division.
(Ord. No. 472-2022. Passed 5-23-22, eff. 5-25-22)