No person shall build, lay, rod, videotape a main sewer, clean, line or pump into any sewer or sewer structure or drain upon private property of the public way without first having obtained a permit from the department of buildings; provided, however, that no permit shall be required for a building's owner, or property manager, or an employee of any of the above to rod or clean any private drain on that property.
No person shall construct any drain or make any connection to any City of Chicago public sewer, private sewer or waterway without first having obtained a permit from the department of buildings, and, if required, from the general superintendent of the Metropolitan Water Reclamation District and any other applicable agencies.
No person shall excavate or make any opening upon the public way or other public place without first having obtained a permit from the department of transportation.
No person shall seal or abandon any sewer or sewer structure unless a permit is first obtained from the department of buildings and the sealing or abandonment is done in the presence of an inspector from the department of buildings.
No person shall uncover or excavate under or around any public sewer, for any purpose, without first having obtained the written consent of the department.
No person shall lay, alter or repair any part of a house drain or drains, or any part of a catch basin or strainer of a house drain or drains, or any part of a cesspool or water closet connecting with any public sewer unless a permit is first obtained from the department of buildings.
Any person who violates this section shall be fined $200.00 for the first offense, and $1,000.00 for the second and any subsequent offense. Any licensed drain layer who violates this section three or more times within any calendar year shall have his license suspended or revoked in accordance with Section 4-28-140 of this Code.
(Added Coun. J. 2-6-02, p. 78883, § 1; Amend Coun. J. 11-13-07, p. 14999, Art. II, § 1)
If the work involves in kind replacement of less than 20 feet of an existing sewer system, or if the work involves rodding, a licensed drain layer may start work without first having obtained a permit if the licensed drain layer (1) calls and registers with the department prior to beginning the work; and (2) pays the permit fees no later than 30 days after the work has been completed; and (3) in the case of in kind replacement, requests an inspection by the department of buildings. If the permit fee is not paid within the required 30 day period, the fee shall double and no new permit under this chapter shall be issued to the licensee until the permit fee is paid.
(Added Coun. J. 2-6-02, p. 78883, § 1; Amend Coun. J. 11-13-07, p. 14999, Art. II, § 1; Amend Coun. J. 11-8-12, p. 38872, § 207)
An application for any permit issued under this chapter shall be made to the commissioner on a form provided by the department of buildings and shall be accompanied by the following:
(1) Any statements, drawings, designs, plans, specifications and related documents showing the location, configuration, dimensions and details of construction of the permitted work as the commissioner may require;
(2) The name and license number of the licensed drain layer who will perform the work, unless the work to be performed is sealing;
(3) A written agreement that the permitted work shall be done in compliance with the requirements of this Code, including, but not limited to, any requirements governing excavation in a public way or public place;
(4) An indemnification agreement as required by Section 11-16-070;
(5) The permit fee; and
(6) Any other information that the commissioner may require.
(Added Coun. J. 2-6-02, p. 78883, § 1; Amend Coun. J. 11-13-07, p. 14999, Art. II, § 1)
No permit shall be issued under this chapter unless the building commissioner approves in writing any statements, drawings, plans, specifications and related documents submitted pursuant to Section 11-16-050(1) of this chapter.
(Added Coun. J. 2-6-02, p. 78883, § 1; Amend Coun. J. 11-13-07, p. 14999, Art. II, § 1)
An applicant for a permit under this chapter shall agree to indemnify, defend and hold the city harmless against all liabilities, judgements, costs and expenses which may in any way result from the issuance of any permit under this chapter.
(Added Coun. J. 2-6-02, p. 78883, § 1)
The building commissioner is authorized to issue permits under this chapter. Permit fees shall be charged as follows:
(a) Connections to public sewers and extensions of private drains.
Six-inch diameter and smaller.....$75.00
Eight-inch diameter.....$125.00
Ten-inch to 16-inch diameter.....$175.00
18-inch to 21-inch diameter.....$225.00
24-inch and larger.....$300.00
Connections by public agencies of branch sewers or catch basin drains to main sewers.....$125.00 – $450.00
(b) Repairs and/or additions to existing sewers up to 20 feet.
Six-inch diameter and smaller.....$65.00
Eight-inch diameter.....$100.00
Over eight-inch diameter.....$125.00
Repairs or adjustment of a sewer structure in public way or on private property.....$50.00
Repair of an existing flood control system on private property.....$30.00
(c) Rodding or cleaning of private drains.....$20.00
(d) Seal permits (demolition).....$125.00
(e) Miscellaneous permit fees:
Sump pump only installation.....$50.00
Sump pump and drain tile installation.....$100.00
Flood control and overhead conversion.....$100.00
Inspection manholes (per manhole).....$100.00
Each townhouse/single-family residence unit of a planned development or subdivision (each house).....$65.00
Pumping water from basements of residential buildings up to six flat apartment buildings.....$30.00
Minimum.....$100.00
Stubs (per stub).....$50.00
Installation of testing equipment in a manhole....$150.00
(f) Fees for videotaping, cleaning, lining and inspections of main sewers:
From zero to 500 linear feet of sewer.....$125.00
From 501 to 1,000 linear feet of sewer.....$200.00
Over 1,000 linear feet of sewer.....$275.00
(g) Other fees:
For sewer-related or building drain-related work applied for pursuant to this chapter with no associated permit fee, including the approved use of a pipe diameter not specified in this section, the commissioner of buildings is authorized to assess a permit fee for such work, based on the city's reasonable cost of issuing and administering the permit.
(Added Coun. J. 2-6-02, p. 78883, § 1; Amend Coun. J. 11-19-03, p. 14216, § 7.6; Amend Coun. J. 11-13-07, p. 14999, Art. II, § 1; Amend Coun. J. 7-29-15, p. 3537, § 3)
Notes
3-12-020 | The hyper-linked material is not part of the Chicago Building Code infobase and therefore is not included herein. The material is included in other provisions of the Chicago Municipal Code. The complete Chicago Municipal Code is available for purchase from American Legal Publishing in both print and Folio® versions. Please click here for the appropriate American Legal order form in printable Adobe® PDF format. For additional information, you may visit American Legal's website by clicking here. |
ARTICLE II. OTHER PROHIBITED ACTIVITIES (11-16-090 et seq.)
Loading...