Upon receipt of an application for a special permit by the Borough of Blossburg the following procedures shall apply in addition to those of Part 3:
A. Within 3 working days following receipt of the application, a complete copy of the application and all accompanying documentation shall be forwarded to the County Planning Commission by registered or certified mail for its review and recommendations. Copies of the application shall also be forwarded to the Borough of Blossburg Planning Commission and Borough of Blossburg Engineer for review and comment.
B. If an application is received that is incomplete, the Borough of Blossburg shall notify the applicant in writing, stating in what respect the application is deficient.
C. If the Borough of Blossburg decides to disapprove an application, it shall notify the applicant, in writing, of the reasons for the disapproval.
D. If the Borough of Blossburg approves an application, it shall file written notification, together with the application and all pertinent information, with the Department of Community and Economic Development, by registered or certified mail, within 5 working days after the date of approval.
E. Before issuing the special permit, the Borough of Blossburg shall allow the Department of Community and Economic Development 30 days, after receipt of the notification by the Department, to review the application and decision made by the Borough of Blossburg.
F. If the Borough of Blossburg does not receive any communication from the Department of Community and Economic Development during the 30-day review period, it may issue a special permit to the applicant.
G. If the Department of Community and Economic Development should decide to disapprove an application, it shall notify the Borough of Blossburg and the applicant, in writing, of the reasons for the disapproval, and the Borough of Blossburg shall not issue the special permit.