Review steps. There are 3 required steps to master planned development approval, which may be completed individually or combined for concurrent review:
(A) Application for master planned development concept plan approval.
(B) Application for detailed development plan approval, which may include a preliminary subdivision plan.
(D) Approval process.
(F) The detailed development plan and preliminary subdivision plan shall be reviewed using the Type III procedure in § 151.233 to ensure substantial compliance with the approved concept plan.
(H) Steps (A) through (C), above, may be combined in any manner, so long as the decision-making sequence follows the above order. Notification and hearings may be combined.
(Ord. 2021-08-02, passed 10-12-2021)