21A.59.060: TIME LIMIT ON APPROVED APPLICATIONS FOR DESIGN REVIEW:
No design review approval shall be valid for a period longer than one year from the date of approval unless a building permit is issued or a complete building plans and building permit applications have been submitted to the Division of Building Services and Licensing. An extension of one year may be granted by the entity that approved the application. Extension requests must be submitted prior to the expiration of the design review approval. (Ord. 24B-23, 2023: Ord. 24-23, 2023: Ord. 14-19, 2019)