A. Temporary Basis: A power to panel permit shall authorize power for construction purposes on a temporary basis only; permanent power must be authorized separately.
B. Permit: At the time power to panel is required to complete construction, the owner or contractor shall apply for and obtain a separate power to panel construction permit. Said permit shall be valid for a sixty (60) day period.
C. Extensions: Thirty (30) day extensions for such permit may be issued upon the approval of building and housing services and upon payment of one-half (1/2) of the original permit fee for each extension.
D. Certificate Of Occupancy: Final electrical approval for permanent power shall be withheld until a certificate of occupancy is issued. Occupancy occurring prior to the issuance of a certificate of occupancy shall result in a discontinuance of all power until occupancy is approved or until occupancy ceases.
E. Expiration: Upon expiration of a power to panel construction permit, all power to the electrical panel shall be discontinued.
F. Fees:
60 day, no issue fee | $20.00 |
30 day extension | 7.00 |
(Ord. 53-86 § 1, 1986: prior code § 5-9-18)